DETERMINANTS OF ROAD CONSTRUCTION PROJECT COMPLETION IN NAIROBI COUNTY, A CASE OF KENYA URBAN ROADS AUTHORITY (KURA) LISTED CONTRACTORS

RITA MWENDIA MURIUKI, DR. MAKORI MORONGE (Ph.D)

Abstract


The main objective of the research study was to establish the determinants of road construction project completion in Nairobi City County. The study specific aim was to evaluate how project manager’s competence influence road construction projects completion in Nairobi City County, to determine how project funds influence road construction projects completion in Nairobi City County, to examine how project equipment influence efficient road construction projects completion in Nairobi City County and to examine how Technology adoption influence efficient road construction projects completion in Nairobi City County. The study was undertaken on all KURA offices in Nairobi. The target population comprised of all members of staff in all IT, Finance, and construction departments. The fact that the organizations’ head offices were all based in Nairobi made the collection of data more convenient, reliable and accurate. The study applied a descriptive research design. The study population comprised of 1,200 members of staff working in KURA in Nairobi. The study applied a stratified random sampling technique to select a sample size of 138 respondents. The gathered data were analysed using descriptive statistics aided by Statistical Package for Social Scientists (SPSS) version 22 and findings presented on tables. Inferential statistics using multiple regression analysis was applied to determine the relationship between the research variables. The study found out that project manager’ competency, project fund, project automated equipment and project technology have positive and significant effect on road construction project completion. Based on the findings above the study concluded that project manager’ competency, project fund, project automated equipment and project technology have an influence in road construction project completion in Nairobi county. The study recommended that project managers should be actively involved in the project from start to the end and that they require to be trained effectively to sharpen their skills hence successfully executes their duties. The study also recommended the implementation of technological systems since it can either act as a medium for change or be the means of achieving a desired change in a project therefore good to employ technology to enable successful completion of construction project.

Key Words: Competence, Project Funding, Equipment, Technology, Road Construction

CITATION:  Muriuki, R. M., & Moronge, M. (2019). Determinants of road construction project completion in Nairobi County, A case of Kenya Urban Roads Authority (KURA) listed contractors. The Strategic Journal of Business & Change Management, 6 (4), 347 – 360.


Full Text:

PDF

References


Adams, M. B. (1994). Agency theory and the internal audit. Managerial Auditing Journal, 9(8), 8-12.

Aghion, P., Akcigit, U., & Howitt, P. (2014). What do we learn from Schumpeterian growth theory?. In Handbook of economic growth (Vol. 2, pp. 515-563). Elsevier.

Ahmad, S., & Schroeder, G., (2016). The impacts of electronic data interchange on delivery performance. Production and Operations Management, 10(1), 16-30.

Al-Momani H., (2016), Examining service quality within construction processes, Technovation, Vol. 20, PP. 643.651

Archer, M., (2006). Culture and agency: The place of culture in social theory. Cambridge University Press.

Battilana, J., Leca, B., & Boxenbaum, E. (2009). 2 how actors change institutions: towards a theory of institutional entrepreneurship. Academy of Management annals, 3(1), 65-107.

Brown A., & Adams J., (2013), Measuring the effect of project management on construction outputs: a new approach, International Journal of Project Management, Vol. 18, PP. 327-335

Callinicos, A., (2008). Making history: agency, structure, and change in social theory (Vol. 3). Brill.

Carrillo, M., & Anumba, C., (2015). Review and implementation of performance management models in construction engineering organizations, Construction Innovation. Vol. 5:203–217

Chan W., & Kumaraswamy M., (2016). An evaluation of construction time performance in the building industry, Building and Environment, Vol. 31, No. 6, PP. 569- 578

Chan, W. K., Wong, F. K., & Scott, D. (2014). Managing construction projects in Korea—the transitional period in the millennium1. International Journal of Project Management, 17(4), 257-263.

Chen, S. P. (2017). Analysis of critical paths in a project network with fuzzy activity times. European Journal of Operational Research, 183(1), 442-459.

Cheung, O., Suen H. & Cheung, W., (2004). PPMS: a Web based construction Project Performance Monitoring System, Automation in Construction, Vol. 13, PP. 361. 376

Collis, J. & Hussey, R. (2015) Business Research: A Practical Guide for Confederation of International Contractors Association and UNEP construction industry—a Review, Building and Environment, 40:135–141

Dai, H., Cao, G. & Su, H., (2016). Management and Construction of the Three Gorges. December 2006, 24, pp. 1225–1229.

Dissanayaka S., & Kumaraswamy M., (1999). Comparing contributors to time and cost performance in building projects, Building and Environment, Vol. 34, PP. 31- 42

Donaldson, L., & Davis, J. H. (1991). Stewardship theory or agency theory: CEO governance and shareholder returns. Australian Journal of management, 16(1), 49-64.

Dubois, D., & Rothwell, W. (2017). Competency-Based Human Resource Management. Davies-Black Publishing

Easterbrook, F. H. (1984). Two agency-cost explanations of dividends. The American economic review, 74(4), 650-659.

Gaturu, N. S. & Muturi, W . (2014). Factors affecting the timeliness of completion of donor- funded projects in Kenya: a case of world agro forestry centre (ICRAF). European Journal of Business Management, 2(1), 189-202

Goodhue, D. L., & Thompson, R. L. (1995). Task technology fit and individual performance. MIS Quarterly, 19, 213-236.

Gunduz, M., & Hanna, S., (2015). Benchmarking change order impacts on productivity for electrical and mechanical projects, Building and Environment, Vol. 40, PP. 1068-1075

Gyula, S., (2013) Construction: Craft to Industry, Spon Press, London, UK

Iyer K. & Jha N., (2015). Factors affecting cost performance: evidence from Indian construction projects, International Journal of Project Management, Vol. 23, PP. 283.295

Iyer, C. & Jha, K., (2016). Critical Factors Affecting Schedule Performance in China, Building and Environment, Vol. 41, PP. 915-925

Jackson K., (2015) Fundamentals of Project Performance Measurement,: [http://alarcos.inf-cr.uclm.es/doc/pgsi/doc/otros/pmbok-2000.pdf]

Jensen, M. C., & Meckling, W. H. (1976). Theory of the firm: Managerial behavior, agency costs and ownership structure. Journal of financial economics, 3(4), 305-360.

Jugdev, K., & Muller, R., (2015). A retrospective look at our evolving understanding of Project Performance Measurement: [http://alarcos.inf-cr.uclm.es/doc/pgsi/doc/otros/pmbok-2000.pdf]

Kemps, M., (2015). Fundamentals of Project Performance Measurement, San diego[http://alarcos.inf-cr.uclm.es/doc/pgsi/doc/otros/pmbok-2000.pdf]

GoK (2017) Report

Kenny, C. (2017) Construction, Corruption, and Developing Countries, World Bank

Kerzner, H. (2015) ‘Project Management – A systems Approach to planning, scheduling

Kuprenas, J. A., & Nasr, E. B. (2017). Cost performance comparison of two public sector project procurement techniques. Journal of management in engineering, 23(3), 114-121.

Lam C., & Tsang T., (2017). Modelling risk allocation decision in construction contracts, International Journal of Project Management Leadership and Management in Engineering, January 2003:56

Leesard, R., (2015) Strategic Management of Large Engineering Projects: Shaping Journal of knowledge management, 4(3), 195-203.

Lehtonen, P. (2013). Role of single-project management in achieving portfolio management efficiency. International Journal of Project Management, 25(1), 56-65.

Lewis, J. (2017). Mastering project management: Applying advanced concepts to systems thinking, control & evaluation, resource allocation. McGraw Hill Professional.

Lewis, L., Hagstrom, E., & Herweijer, H. (2014). Efficient delivery of siRNA for inhibition of gene expression in postnatal mice. Nature genetics, 32(1), 107-108.

Lucia, A., & Lepsinger, R., (2009). The Art and Science of Competency Models: Pinpointing Critical Success Factors in Organizations. Pfeiffer Macmillan. The UK.

Mahoney, J., & Thelen, K. (Eds.). (2009). Explaining institutional change: ambiguity, agency, and power. Cambridge University Press.

Marasini, R., & Dawood, N., (2016) Innovative managerial control system (IMCS): a Market Research: An International Journal, 3(2): 82-89, MCB UP

Mišić, S., & Radujković, M. (2015). Critical drivers of megaprojects success and failure. Procedia Engineering, 122, 71-80.

Mitnick, B., (2005). The theory of agency. Public Choice, 24(1), 27-42.

Mugenda, M., & Mugenda, G. A. (2009). Research methods, qualitative and qualitative approaches. Acts Press Nairobi.

Mugenda, O., & Mugenda, A.G. (2003): revised. Research Methods; Quantitative Qualitative Approaches: ACTS Press, Nairobi.

Mwangu, A. W., & Iravo, M. A. (2015). How monitoring and evaluation affects the outcome of constituency development Fund Projects in Kenya: a case study of projects in Gatanga Constituency. International Journal of Academic Research in Business and Social Sciences, 5(3), 13-31.

Ngacho, C., & Das, D. (2015). A performance evaluation framework of construction projects: insights from literature. International Journal of Project Organisation and Management, 7(2), 151-173.

Nguyen, T. P., & Chileshe, N. (2015). Revisiting the construction project failure factors in Vietnam. Built Environment Project and Asset Management, 5(4), 398-416.

Nitithamyong, P. & Skibniewski, J. (2016) Success/Failure Factors and Performance Norwegian University of science and Technology, NTNU. http://www.concept.ntnu.no/ November 11, 2007

Orodho, A. J., & Kombo, D. K. (2002). Research methods. Nairobi: Kenyatta University, Institute of Open Learning.

Orodho, J. A. (2009). Elements of education and social science research methods. Nairobi/Maseno, 126-133.

Orodho, J., (2003). Essentials of educational and social science research methods. Nairobi: Mazola Publishers.

Orodho, J., A. (2004). Techniques of writing research proposals and reports in education and social sciences. Nairobi: Masola Publishers.

Payne, J., & Turner, R., (2014) Company –wide project management: planning and control of programs of projects of different types. International Journal of project management, 17(1):55-59

Pearman, R., (2016) Contractors look abroad for high-rise expertise, Contract Journal, 435 (6597) Pearson Education Ltd., Esssex

PMI (2015). Organizational Project Management Maturity Model (OPM3), Retrieved Policy Research Working Paper No. 4271, June 2015.

Polonsky, J., & Waller, D., (2005). Designing and Managing a Research Project: A business student’s guide, Sage, the USA

Potter, W., (2006). An analysis of thinking and research about qualitative methods, LEA, Publishers, New Jersey.

Proverbs, D. G., Holt, G. D., & Olomolaiye, P. O. (1998). Factors impacting construction project duration: a comparison between France, Germany and the UK. Building and environment, 34 (2), 197-204.

Reschke, H., & Schelle, H., (2013). Dimensions of Project Management – Fundamentals, techniques, Organization, Application, Springer-Verlag Berlin, Heidelberg, Germany Retrieved: 2007-11-11

Ross, S. (2008). The economic theory of agency: The principal's problem. The American Economic Review, 134-139.

Rumsey, J. (2011). Statistics for dummies. John Wiley & Sons. Viewpoint, Journal of Construction Engineering and Management, January 2006

Sambasivan, M. & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry, International Journal of Project Management, 25: 517–526

Saunders, M., Lewis, P. & Thornhill, A. (2007). Research Methods for Business September / October 2009, pp.570.

Seboru, M. A. (2015). An investigation into factors causing delays in road construction projects in Kenya. American Journal of Civil Engineering, 3(3), 51-63.

Shandler, D. (2016). Competency and the Learning Organization. Crisp Learning. International Journal of Project Management, 25: 517–123

Spencer, L., & Spencer, S. (2008). Competence at Work: Models for Superior Performance.

Strenman J. D. (2012) ‘System dynamics modelling for project management’ Sloan School Students, 3rd Ed, Pearson Education Limited, England

Vandevoorde, S., & Vanhoucke, M. (2016). A comparison of different project duration forecasting methods using earned value metrics. International journal of project management, 24(4), 289-302.

Wang, X., & Huang, J. (2016). The relationships between key stakeholders’ project performance and project success: Perceptions of Chinese construction supervising engineers. International Journal of Project Management, 24(3), 253-260.

Waweru, P. K., & Omwenga, J. (2015). The Influence of Strategic Management Practices on Performance of Private Construction Firms in Kenya. International Journal of Scientific and Research Publications, 5(6), 1-36.

World Bank, (20016). Infrastructure Assessment, Finance, Private Sector and Infrastructure Group. Middle East & North Africa, December 2004

World Development Report 2012. Gender Equality and Development. World Bank. © World Bank. License: CC BY 3.0 IGO.




DOI: http://dx.doi.org/10.61426/sjbcm.v6i4.1389

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 2 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 1 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
  Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
  Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.