EFFECT OF PROJECT MANAGEMENT PRACTICES ON IMPLEMENTATION OF HOUSING DEVELOPMENT PROJECTS IN KENYA: A CASE STUDY OF KENYA PROPERTY DEVELOPERS ASSOCIATION

FREDERICK ETYANG EMOYO, DR. TITUS MUTHAMI KISING’U (Ph.D), JACOB JUMA OYOO

Abstract


The study was on the effects of project management practices on implementation of housing development projects in Kenya. The study used descriptive research design. The target population in this research were 241 employees in 15 selected registered property developers in Mombasa County. Stratified sampling technique was used to select a sample size of 149 respondents. Primary data was collected by use of self-administered structured questionnaires. The secondary data collected was used to cross validate the primary data results. The collected data was analyzed quantitatively and qualitatively. Descriptive and inferential statistics was done using Statistical Package for Social Sciences (SPSS) version 24 and specifically multiple regression model was used for hypotheses testing. The study findings established that three objective namely project team competency, project planning and project stakeholders’ management had a positive correlation with implementation of housing development projects in Kenya. However, the independent variable project cost management had no correlation with the dependent variable. On regression analysis results rejected null hypotheses for project team competency, project planning and project stakeholders’ management but accepted the null hypothesis for project cost management . The study conluded that project team competency, project planning and project stakeholders’ management have a significant effect on implementation of housing development projects in Kenya and further concluded that project cost management has no significant effect on implementation of housing development projects in Kenya. The study recommended that staff working in a projects needs to be trained before projects commences; that projects should hire project managers that have project academic and practical experience; that projects are financed after proper evaluation of projects viability by quantity surveyors’, that project managers should adopt the use of innovation and technology in their project planning process that would be accurate and that project stakeholders’ should be involved in all milestones of the projects to enrich the project in cases of variances in costing.

Key Words: Project Team Competence, Cost Management, Project Planning, Stakeholder Management

CITATION: Emoyo,  F. E., & Kising’u, T. M. (2019). Effect of project management practices on implementation of housing development projects in Kenya: A case study of Kenya Property Developers Association. The Strategic Journal of Business & Change Management, 6 (4), 1276 – 1292.


Full Text:

PDF

References


Abisuga, A. O., Amusu, O. R., & Salvador, K. A. (2018). Construction delay in Nigeria:A perception of indigenous and multinational construction firms. Journal of Emerging Trends in Economics and Management Science, 5 (3), 371 - 378.

Akintoye, A., & Takim, R. (2016). Performance Indicators for Successful Construction Project Performance:In Greenwood, D (Ed). . 18th Annual ARCOM Conference (pp. 545-555). Washington DC: Harvard Press.

Akinwunmi, A. A. (2018). An investigation into factors affecting housing finance supply in emerging economies:A case study of Nigeria. Journal of the University of Wolverhampton, 12 (3), 45 - 62.

Alaghbari, W., Kadir, K., Salim, A., & Ernawati, T. (2017). Delay factors impacting construction projects in Yemen. PM Journal, 12 (7), 90 - 109.

Alexandrova, M., & Ivanova, L. (2016). Critical success factors of project management. International Journal of Social Sciences and Entrepreneurship, 1 (12), 9.

Anvuur, T., & Kumaraswamy, T. (2017). An investigation into the training of Labour in the informal construction sector in Kenya. Unpublished Doctoral Thesis University of Cape Town, Retrieved from https://www.uoct.ac.za.

Atkinson, D. (2013). Urbanization and the futire urban agenda in South Africa. Cape Town: Human Science Research Council.

Barksdale, J., & Lund, P. (2016). Pro-poor housing policies:Rethinking the potential of assisted self help housing. Habitat International, 34, 278-287.

Bryman, A., & Bell, E. (2013). Business Research Methods. London: Oxford University Press.

Bui, T., & Ling, F. (2017). Factors Affecting Construction Projects Outcomes:Case Study of Vietnam. Washington DC: McGrawHill Publishers.

Chinyio, E., & Olomolaiye, P. O. (2018). Construction Stakeholders' Management. London: Thomas Telford.

Cleland, D. I., & Ireland, L. R. (2017). Project Management:Strategic Design and Implementation. New York: McGrawhill Publishers.

Cooper, R., & Schinder, S. (2014). Business Research Methods. New York: McGrawHill.

Ericksson, P. E. (2014). Efficient governance of construction projects through cooperative procurement procedures. Business Administration and Management, 123.

Gandy, M. (2017). Planning, anti-planning and the infrastructure crisi facing Metropolitan Lagos. Lagos: Lagos House of Publishing.

Gerry-Johnson, M. (2015). A critical success factors model for enterprise resource planning implementation. Proceedings of the 7th European Conference on Information Systems,. Vienna.

Ghahramanzadeh, M. (2013). Managing Risk of Construction Projects:A case study of Iran. University of East London, 56, (2) 89.

Githenya, M. S., & Ngugi, K. (2018). Assessment of the Determinants of Implementation of Housing Projects in Kenya. European Journal of Business Management, , 1 (11) 230-253.

GoK. (2018). Statistical Abstract. Nairobi: Government Press.

Gong, M. Z., & Tse, M. S. (2013). Picl, mix or match? A discussion of theories for management accounting research. Journal of Accounting Business and Management, 16 (2), 54-66.

Graham, N. (2014). Project Management for Dummies. London: Sage Publishers.

Hassanali, F. M. (2016). Understanding reduced private sector participation in low housing delivery in Nairobi. Nairobi: ACTS Press.

Haughey, D. (2015). Project Management Body of Knowledge. London: Oxford University Press.

Huchzermeyer, W. (2018). Causes and Effects of delys in large construction projects of Pakistan. Arabian Journal of Business and Management Review, 1 (4), 18-42.

Iya, K., & Tha, K. (2017). Critical factors affecting schedule performance: Evidence from Indian construction projects. Journal of Construction Engineering and Management, 132(8):871– 881.

Kabacia, V. W. (2017). Management practices influencing performance of road construction projects:A case of Imenti North SubCounty Meru, Kenya. Journal of Construction Projects, 1 (2), 45 - 63.

Kast, T., & Rosenzweig, T. (2018). Factors influencing project completion in the housing construction industry. Belmount: Wadsworth Publishers.

Kerzner, H. (2014). Project Management:A System Approach to Planning, Schedulling and Controlling. London: Wiley & Sons Limited.

Kibuchi, N., & Muchungu, P. (2018). The contribution of human factors in the performance of construction projects in Kenya:A case study of construction project team participants in Nairobi. Journal of Strategic Project Management, 12 (3), 5 -14.

Lam, S. Y., & Tang, C. H. (2014). Motivation of survey employees in construction projects. Journal of Geospatial Engineering, 5 (1), 61-66.

Laufer, A., Denker, G. R., & Shenhar, A. J. (2018). Simultaneous management: the key to execellence in capital projects. International Journal of Project Management, 14, 189-199.

Mukiibi, S. (2016). Housing policies on the supply of housing to urban low-income earners in Uganda:A case study of Kampala. University of Newcastle Upon Tyne, 45 (10) 123.

Nyaga, K. G., & Otieno, M. (2018). Role of project management skills on performance of construction firms in Mombasa County, Kenya. International Journal of Project Management, 12 (2), 5 - 9.

Otiso, K. M. (2017). State, Voluntary and private sector partnerships for slum upgrading and basic service delivery in Nairobi City. Journal of Public Planning, 67, (1) 900-911.

Phua, F. T., & Rowlinson, S. (2013). How important is cooperation to construction project success?A grounded empirical quantification. Engineering, Construction and Architectural Management, 11 (1), 45-54.

Pinto, W., & Morris, W. (2014). Project implementation phase and project life cycle. Jopurnal of Project Management, 14 (7) 90.

Saunder, M., Lewis, P., & Thornhill, A. (2013). Research Methods for Business Students (5th Ed). Washington DC: Prentice Hall, Financial Times.

Seddon, J. (2016). Construction process improvement methodology for construction projects. International Journal of Project Management, 16 (4), 215 - 221.

Sekaran, U., & Bougie, R. (2014). Research methods for business:A skill building approach. New Jersey: John Wiley & Sons.

Shaban, S. S. (2014). Factors affecting the performance of construction projects in the Gaza strip. The Islamic University of Gaza, 12 (4), 85 - 96.

Sidwell, A. C. (2015). The time performance of construction projects. Architectural Science Review, 27, 85-91.

Simon, L., & Jamal, A. M. (2017). Effects of Financial Management Practices on Financial Performance for County Governments in Kenya-A Case Study of Mombasa County. Imperial Journal of Interdisciplinary Research, 3 (9), 1097-1109.

Statistical Abstract. (2018). Economic Survey, Kenya. Nairobi: Kenya National Bureau of Statictics.

Triantis, J. E. (2013). Creating successful acquisition and joint venture projects:A process and team approach. Washington DC: Greenwood Publishing Group.

UN-Habitat. (2018). State of African Cities 2018:A framework for addressing urban challenges in Africa. Nairobi: ACTS Press.

Yeo, W. (2014). Causes and effectss of delay in Malaysian constrcution industry. International Journal of Project Management, 25, 517-526.




DOI: http://dx.doi.org/10.61426/sjbcm.v6i4.1464

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 2 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 1 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
  Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
  Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.