EFFECT OF STAKEHOLDER FACTORS ON COMPLETION OF ROAD CONSTRUCTION PROJECTS IN KENYA: A CASE STUDY OF KISII COUNTY

DANIEL OKINYI OUMA, DR. JANE QUEEN OMWENGA (PhD)

Abstract


This study explored the effect of stakeholder factors on completion of road construction projects in Kenya with specific objectives being client related factors, contractor related factors, consultant related factors, and external factors. Contingency theory, Expectancy theory, theory of planned behaviour and stakeholder theory were the anchors of the study. The instruments of data collection were structured questionnaires. The target population consisted of 80 project managers, road engineers, project managers, road supervisors, road inspectors, road surveyors and contractors in Kisii County. The unit of analysis were on-going and completed road projects implemented by Kisii county government. Simple random sampling was used to select 80 of whom 70 respondents returned the questionnaires representing 87% respondents. This study produced both quantitative and qualitative data. Once the questionnaires were received, they were coded and edited for completeness and consistency. Analysis of quantitative data was done by using descriptive statistics and inferential analysis using statistical package for social science (SPSS) version 24. The findings showed that client related factors had a significant positive relationship with project completion. 30.9% of the variation in project completion can be attributed to the factors associated with the client. Contractor related factors had a statistically significant positive relationship with project completion. From regression analysis, 33.4% of the variation in project completion can be attributed to contractor related factors. Consultant related factors had a statistically significant positive relationship with project completion. 14.8% of the variation in project completion can be attributed to consultant related factors. External factors had a statistically significant positive relationship with project completion accounting for 28.9% for its variation. Clients should ensure there are enough funds to finance the project without delaying any payment to the contractor. Contractors selected for any construction project should have enough financial capacity and adequate equipment of the right quality and should have some control over sub-contractors. This would ensure the project is completed within budget, time and meet client specifications. Consultants should be present on site to supervise project activities and also communicate effectively any information including variation orders, design documents, and sample materials to the client and contractor promptly.

Keywords: Client, Contractor, Consultant, Road Construction

CITATION: Ouma, D. O., & Omwenga, J. (2021). Effect of stakeholder factors on completion of road construction projects in Kenya: A case study of Kisii County. The Strategic Journal of Business & Change Management, 8 (4), 14 – 26.


Full Text:

PDF

References


A. Twort & G. Rees ,. (2004). Civil Engineering Project Management (4th Ed.).

Abdalla G. & Hussein R. . (2001). Causes of delays in construction in Industry in Jordan. Volume 3, Jordan.

Abd El-Razek, M., Bassioni, H., & Mobarak, A. (2008). Causes of delay in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831-841

Ahmadi, A., & Golabchi, M. (2013). Complexity theory in construction project time management. International Research Journal of Applied and Basic Sciences, 6(5), 538-542.

Bartlett, J. E., Kotrlik, J. W., & Higgins, C. C. (2001). Organizational Research: Determining Appropriate Sample Size in Survey Research Appropriate Sample Size in Survey Research. Information Technology, Learning and Performance Journal, 19(1), 43-50.

Braimah, N. (2013). Construction Delay Analysis Techniques—A Review of Application Issues and Improvement Needs. Buildings, 3(3), 506-531.

Chabota, M. & Kanyuka, N. (2008). The Performance of Infrastructure projects in Developing Countries, Zambia.

Choge, J., & Muturi, W. (2014). Factors affecting adherence to cost estimates: A survey of construction projects of Kenya National Highways Authority. International Journal of Social Sciences and Entrepreneurship, 1(11), 689-705.

Cooke, H. & Tate, K. . (2008). Project Management, (2nd Ed),. Mc-Graw-Hills publishers, New Delhi. .

Dadzie, J., Abdul-Aziz, A., & Kwame, A. (2012). Performance of consultants on government projects in Ghana: Client and contractor perspective. International Journal of Business and Social Research, 2(6), 256-267.

Edmonds, G. (1980). The Roads and Labour programme: Appropriate Technology in Road Construction in Developing Countries, London.

Federation Internationale Des Ingenieurs Conseils (FIDIC). (1992). Conditions of contract for works of civil Engineering construction, Thomas Telford, London.

Fugar, F. D., & Agyakwah-Baah, A. B. (2010). Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, 10(1/2), 128

Gaturu, N., & Muturi, W. (2014). Factors affecting the timeliness of completion of donor-funded projects in Kenya: a case of world agro forestry centre (ICRAF). European Journal of Business Management, 2(1), 189-202.

Gerard, M. H. (2008). The Complete Project Management Office Handbook.

Government of the Republic of Kenya. (1979). Road design Manual Part1, Roads Department, Nairobi .

Government of the Republic of Kenya. (2007). Ministry of Transport and Communication, Nairobi; Standard Specification for Road and Bridge Construction.

Gray, T. &. (2008). Project Management: The Managerial Process (4th ed.) McGraw-Hill Irwin. .

Gupta, M. C., & Boyd, L. H. (2008). Theory of constraints: a theory for operations management. International Journal of Operations & Production Management, 28(10), 991-1012.

K., C. H. (2008). Project Management, (2nd Ed). Mc-Graw-Hills publishers, New Delhi.

Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of project management, 27(5), 522-531.

Kamau, G., & Muturi, M. Factors Affecting Successful Completion of Constituency Development Funded Projects in Kenya: A Case Of Nyandarua County. International Journal of Economics, Commerce and Management, 3(5), 499-516.

Kamotho, J. M. (2014). Factors Influencing Project Completion in the Housing Construction Industry, Nairobi County. (MA Thesis), University of Nairobi.

M.W., A. (1979). Engineering Law and International Consulting Engineers’ Contracts,. 4th Edition, Books Ltd, London. .

Mugenda, O. M. (2003). Research methods, Laba graphic services: Nairobi. .

Muhwezi, L., Acai, J., & Otim, G. (2014). An assessment of the factors causing delays on building construction projects in Uganda. International Journal of Construction Engineering and Management, 3(1), 13-23.

Musa, M. M., Amirudin, R. B., Sofield, T., & Musa, M. A. (2015). Influence of external environmental factors on the success of public housing projects in developing countries. Construction Economics and Building, 15(4), 30-44.

Mydin, M. O., Sani, N. M., Salim, N. A., & Alias, N. M. (2014). Assessment of Influential Causes of Construction Project Delay in Malaysian Private Housing from Developer’s Viewpoint. Paper presented at the E3S Web of Conferences.

Murali, N. & Wen, H. . (2007). Causes of Delays in Construction Industry, Malysia.

Olatunji, A. A. (2010). Influences on construction project delivery time. (PhD Thesis), Nelson Mandela Metropolitan University.

Ondari, P., & Gekara, J. (2013). Factors influencing successful completion of roads projects in Kenya. International Journal of Social Sciences and Entrepreneurship, 1(6), 26-48.

Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of project management, 25(5), 517-526.

Van, L. T., Sang, N. M., & Viet, N. T. (2015). A Conceptual Model of Delay Factors affecting Government Construction Projects. ARPN Journal of Science and Technology, 5(2), 92-100.




DOI: http://dx.doi.org/10.61426/sjbcm.v8i4.2082

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 2 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 1 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
  Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
  Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.