PROJECT PLANNING PROCESSES AND STRATEGIC PERFORMANCE MANAGEMENT IN GAHAYA LINKS PROJECTS IN KICUKIRO DISTRICT RWANDA: A CASE OF GAHAYA LINKS BASKET PROJECT KICUKIRO DISTRICT

ELIE NGABONZIMA, DR. ALICE KITUYI WAFULA (PhD)

Abstract


The purpose of this study was to investigate the influence of project planning processes and strategic performance management in Gahaya links projects in Kicukiro district Rwanda. The study focused on: scope planning, risk planning and dissemination planning on strategic performance management in Gahaya links projects in Kicukiro district Rwanda. The study adopted a descriptive survey design. The research was carried out by using secondary data, from the relevant documents obtained from Gahaya Link’s office, whereas the primary data was collected using questionnaire. The research analysis and interpretations were based on respondents’ responses. The respondents were provided with questionnaires, interview and observation, applying different techniques, motivation and each item contributed would give rise to a variable. The researcher asked participants to scrutinize instruments for face to face and content validity. For reliability, test-retest method was used. The coefficient of Cronbach was used to establish how reliable the instruments are. Test value of 0.700 was termed well enough and the tools was judged reliable. Concurrent triangulation was used to ensure credibility. An in-depth interview was applied to establish dependability of non-numerical instruments. Quantitative data was analyzed through descriptive and inferential statistical tests, as well as presented through tables and figures. Descriptive statistical tests include percentages, frequencies and counts while inferential statistical tests entail multiple regression. Majority of the respondents consisting of 53.1% agreed that in Gahaya links project, Work Breakdown Structure is always created along with providing guidance for schedule development and control to ensure timeliness in project delivery, 34.4% strongly agreed, 12.5% were undecided and none disagreed. Majority of 46.9% agreed, 39.1% strongly agreed, 12.5% were undecided, 1.6% disagreed and none strongly disagreed. Majority of the respondents consisting of 42.2% agreed that in Project risk identification in Gahaya links project is done to ensure strategic performance management of the project, 42.2% strongly agreed, 9.4% were undecided and 6.3% disagreed. As to whether Gahaya links project, we have developed a model that we apply to correctly identify, respond and monitor risks to save time and money to ensure timeliness in delivery of products, majority of the respondents consisting of 60.9% strongly agreed, 21.9% agreed, 12.5% were undecided and 4.7% disagreed. Another statement related to review process was asked. The respondents were required to rate their opinion as to whether in Gahaya links project, there is a review process after the application of the mitigation measures for the identified uncertainties to ensure project success. Finally respondents opinion was sought on whether project managers effectively manager evaluates and records potential and identified uncertainties to ensure project success. Fifty four point seven percent strongly agreed, 25% agreed, 17.2% were undecided, 3.1% disagreed none strongly disagreed.  The study concludes that definition of project scope helps in identifying major project work components, deliverables, and requirements. In addition creating work breakdown structure provides the necessary framework for detailed cost estimating and control, along with providing guidance for schedule development and control. The study recommends that since dissemination planning is one of the most important plans in a project. On project scope planning the study recommends that there is need to develop a clear project scope that can facilitate for the project organization to realize the actual magnitude of the work and creates an understanding for the achievements that are required in the project. Further studies that seek to illustrate how much of the variation in project performance can be explained by the various resource planning practices within Gahaya Links Project should be conducted.

Keywords: Scope planning, Risk planning, Dissemination planning, Strategic performance management, Gahaya links projects, Kicukiro district, Rwanda

 CITATION: Ngabonzima, E., & Wafula, A. K. (2022). Project planning processes and strategic performance management in Gahaya links projects in Kicukiro District Rwanda: A case of Gahaya Links Basket Project Kicukiro District. The Strategic Journal of Business & Change Management, 9 (4), 729 – 743.


Full Text:

PDF

References


Adan, I. H. (2012). Influence of stakeholder’s role on performance of constituencies development fund projects a case of Isiolo North Constituency, Kenya. Unpublished Masters in project planning and management, University of Nairobi.

Ali, D., & Gelsdorf, K. (2012). Risk-averse to risk-willing: Learning from the 2011 Somalia cash response. Global Food Security, 1(1), 57-63

Asian Development Bank (2011). Improving project Success through Effective Communication and Participation.

Belassi, W. and Tukel, O.I., (2016). A new framework for determining critical success/failure factors in projects. International journal of project management, 14 (3), 141– 151.

Bryman, A. (2011). Social Research Methods. New York: Oxford Publishers

Burgan, S. C. & Burgan, D. S. (2012). A case study on the adoption of project management in an Organization. Paper presented at PMI® Global Congress 2012—North America, Vancouver, British Columbia, Canada

Cheruiyot p. (2017). Effect of Public Financial Management Practices on Performance of County Governments in Kenya. Unpublished thesis.

Coldham, N.P. (2013). Empower Rwandan women entrepreneurs: The gendered enterprises of Nation-building. Unpublished Master’s thesis, Royal Roads University, Victoria.

Cooper, D. R., & Schindler, P. S. (2011). Business Research Methods (11th ed.). New York: McGraw-Hill/Irwin.

Creswell, J., (2014). Research Design: Qualitative, Quantitative, and Mixed Methods Approaches. India: SAGE Publications. 4th Ed.

Cronbach. (1951). Coefficient Alpha? An Examination of Theory and Applications. Journal of Applied Psychology, 78(1), 98-104

Ekundayo, D., Jewell, C., & Awodele, O. A. (2013). Executive Project Management Structure and the Challenges Facing its Adoption in the Nigerian Construction. International Journal of Architecture, Engineering and Construction, vol2(3):158-169.

Field, A. (2013). Discovering statistics using IBM SPSS Statistics, London: Sage.

Gibson, G.E., & Hamilton M.H. (2014). Analysis of pre-project planning effort and success variables for capital facility projects. Rep. SD-105. Construction Industry Institute, University of Texas at Austin, Austin

Gichoya, D. (2012). Factors Affecting the Successful Implementation of ICT Projects in Government. Journal of e-Government, 3(4), 175-184

Golini, R., Kalchschmidt, M., & Landoni, P. (2015). Adoption of project management practices: The impact on international development projects of nongovernmental organizations. International journal of project management, 33(3), 650-663.

Government of Rwanda, (2013). Economic Development and Poverty Reduction Strategy 2013 – 2018, Kigali: Government of Rwanda.

Gujarat, D.N. & Porter, D.C, (2016). Essentials of econometrics. London: McGraw-Hill International.

Ibrahim, A. D. (2011). Investigating Into the Knowledge Requirements of Nigerian Quantity Surveyors to Meet Future Challenges. 25th Biennial Conference of The NIQS (pp. 7-18). Abuja: NIQS.

Ika, L. A. (2012). Project management that facilitates sustainable development in Africa: The reason why projects are having challenges and possible mitigation. Project management journal, 47(1), 32-35.

Ika, L. A., Diallo, A., & Thuillier, D. (2012). Critical Success Factors: An Empirical Investigation. International Journal of Project Management, 30 (2012) 105- 116.

Hirwa, P. (2010). The impact of women entrepreneurs on economic development of Rwanda – Case study of women entrepreneur in expo 2010 organized by Rwanda private sector federation. Universite Nationale du Rwanda - A0 2010

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Karzner, H. (2013). Project Management: A systems approach to planning, scheduling and controlling. New York: John Wiley and Sons.

Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and controlling. New Jersey: ohn Wiley & Sons.

Kerzner, H. (2018). Project management best activities: Achieving global excellence. New Jersey: John Wiley & Sons.

Kerzner, H. (2019). Using the project management maturity model: strategic planning for project management. New Jersey: John Wiley & Sons.

Khan, D. B. (2013). Measuring Project Success in the Construction Industry. Electronic Journal of Business Research Methods, 6(1), 43-52.

Kombo, D. & Tromp, D. (2016). Proposal and Thesis Writing: An Introduction. Nairobi: Pauline Publications Africa.

Kothari, C., & Garg, G., (2014). Research Methodology. New Delhi: New Age International (P) Ltd. Publishers.

Kothari, C.R. & Gaurav, G. (2014). Research Methodology, (3rd Ed.), New Delhi: New Age International Publishers.

Kothari, C.R. (2012). Research Methodology, Methods and Techniques. New Delhi: Kaveri Book Service.

Lester, A. (2017). Project Management, Planning and Controle. Seventh Ed. Brian Guerin (ed.). Joe Hayton. (p7).

Mugenda M. O. and Mugenda A. (2013), Research Methods: Qualitative and Quantitative Approaches, African Centre for Technology Studies, Nairobi.

Mugenda, A.G. (2012). Qualitative research methods. Nairobi: Applied Research and Training Services

Müller, R., & Jugdev, K. (2012). Critical success factors in projects: Pinto, Slevin, and Prescott–the elucidation of project success. International journal of managing projects in business, 5(4), 757- 775.

Musa, H., Ibrahim, Y. M., & Ibrahim, A. D. (2011). On the accuracy of cost estimates: Identifying flaws in Bills of Quantities for Building Projects in Nigeria. Procs West Africa Built Environment Research (WABER) Conference, 19-21 July 2011, (pp. 761-769). Accra-Ghana: Laryea, S., Leiringer, R. and Hughes, W. (Eds).

Musirikare A.M. & Kule JW. 2016. Project Delays on Cost Overrun Risks: A Study of Gasabo District Construction Projects Kigali, Rwanda ABC Journal of Advanced Research, 5, 21-34.

Musomandera, L., Shukla, J. & Luvanda, A. (2015). Microfinance and business growth of women small and medium enterprises in Rwanda. European Journal of Accounting, Auditing and Finance Research, 3(11): 26-39.

Muszynska, K. (2015). Communication Management in Project Teams (Practices and Patterns): Paper Presented at Management, Knowledge and Learning Joint International Conference 2015, Bari, Italy

Namusonge, G.S (2010). Business Statistics: Concepts and Applications. Beau Bassein, Mauritius: VDM Publishing House Ltd.

Nasiru, Z. M., Kunya, S. U., & Abdurrahman, M. (2012). Assessment of Factors that Affect Cost Control by Nigerian Construction Contractors. Journal of Engineering and Applied Science, 71-79.

Ngechu. M. (2012). Understanding the research process and methods. An introduction to research methods. Nairobi: Acts Press.

Olatunji, A. A. (2010). Influences on Construction Project Delivery Time. South Africa: PhD Thesis NMMU.

Oluoch O. (2021). Strategic leadership and financial sustainability of non-governmental organizations in Kenya. American Journal of Leadership and Governance, 1(1), 82-95.

Ondari, P. O. & Gekara, J. M. (2013). Factors influencing successful completion of roads projects in Kenya. International Journal of Social Sciences and Entrepreneurship, 1(6), 26-48.

Orodho, J.A. (2015). Elements of Education and Social Research Methods. Nairobi: Masola Publishers.

Oso, W. & Onen, D. (2011). A General Guide to Writing Research Proposal and Report; Handbook for Beginning Researchers. Nairobi: Jomo Kenyatta Foundation.

Parlani, F. (2017). Managing product development as a project: business process modeling, Unpublished Master's thesis, Πειραιώς: Πανεπιστήμιο Πειραιώς.

Palmer, M. A. (2014). The Architect’s Guide to Facility Programming. Washington DC: The American Institute of Architects.

Pirozzi, M. (2018). The stakeholder management perspective to increase the success rate of complex projects. PM World Journal, 7, 1-12.

Project Management Institute (2013). A guide to the project management body of knowledge, (8th ed,). Newtown Square, PA: Project Management Institute

Ramabodu, M. S., & Verster, J. J. (2013). Factors that influence cost overruns in South African public sector mega-projects. International Journal of Project Organization and Management, 5(1-2), 48-56.

Ravallion, M. (2011). ‘On Multidimensional Indices of Poverty’, World Bank Policy Research Working Papers, 5580.

Richard M. (2012). The Top Reasons Projects Are Unsuccessful. PM World Journal. 1(5) December 2012

Roeder, T. (2013). Managing project stakeholders: building a foundation to achieve project goals. New York: John Wiley & Sons.

Rukundo, J.B. 2015. Understanding informal sector employment in Rwanda. International Review of Research in Emerging Markets and the Global Economy, 1(2): 295-309.

Saunders, M., Lewis, P., & Thornhill, A. (2016). Research methods for business students. 7 th ed. Pearson education.

Sekaran, U., & Bougie, R. (2011). Research Methods for Business: A Skill Building Approach. (5eds.). New Delhi: John Wiley & Sons.

Sethi, R., & Philippines, R. (2012). The influence of project managers on project success criteria and project success by type of project. European Management Journal, 25(4), 298-309.

Shaban, N. (201I). Overview of policies and legal framework for promoting women in socio-economic development and in business in the partner’s states. Paper presented at the EAC Conference on the role of women in socio-economic development in business Kigali, Rwanda.

Slevin, D. P. & Pinto, J. K. (2011). The Project Implementation Profile: New Tool for Project Managers. Project Management Journal, 10(4), 57-70.

Shrenash, R., Pimplikar, S., & Sawant, K. (2013). Effect of project cost and time monitoring on progress of construction project. International Journal of Research in Engineering and Technology, 2, 12.

Sözüer, M., & Spang, K. (2014). The importance of project management in the planning process of transport infrastructure projects in Germany. Proceeding Social and Behavioral Sciences, 119, 601-610.

Sweis, G.J. (2013). Factors Affecting Time Overruns in Public Construction Projects: The Case of Jordan. International Journal of Business and Management, 8(23), 23-34.

Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), 1382-1394.

Turner, R., & Zolin, R. (2012). Forecasting success on large projects: developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames. Project Management Journal, 43(5), 87-99.

Turner, R, & Zolin, R. (2012). 'Forecasting success on large projects: developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames', Project Management Journal 43.5, pp. 87-99.

USAID (2010). Weaving peace in Rwanda. Global report. April 2010.

Verzuh, E. (2015). The fast forward MBA in project management. New York: John Wiley & Sons

Wachuru, S. K., & Amuhaya, M. I. (2013). The Role of Risk Management Activities in the Success Performance of Constituency Development Fund Projects: A Survey of JUJA Constituency Kiambu-Kenya. International Journal of Academic Research in Business and Social Sciences, 3(7), 423.

Walker, A. (2015). Project management in construction. Sixth. John Wiley & Sons.page155-158

Wanderi, E. (2015). Factors Influencing Implementation of Total Quality Management in Construction Companies in Rwanda: A Case of Fair Construction Company. Master’s Thesis. Jomo Kenyatta University of Agriculture and Technology.

Watch, L. (2013). The Capacity of NGOs to Become Sustainable by Creating Social Enterprises. Journal of Small Business and Entrepreneurship Development, 2(2), 01- 36.

Windapo, A. (2013). Fundamentals of Construction Management. Ventures Publishing ApS




DOI: http://dx.doi.org/10.61426/sjbcm.v9i4.2446

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 2 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 1 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
  Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
  Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.