INFLUENCE OF PROJECT LIFE CYCLE MANAGEMENT ON COMPLETION OF PUBLIC PROJECTS IN KENYA: A CASE OF MAKUENI CONSTITUENCY

FESTUS M. MAUNDA

Abstract


In developing countries, national and regional governments, local and international NGOs and other concerned organizations invest large sums of money every year for the implementation of public projects However, in Kenya, public projects are characterized with low or poor completion  and do not meet their objectives if they fail after a short time. In order to make the investment in public projects more effective, failure rates of these systems should be reduced. It has been observed that failure by communities and other stakeholders to take up ownership of public projects have plunged these projects into immense financial huddles threatening their completion and consequently to seize operations. Community issues such as perceived lack of ownership, lack of education on public projects, poor management systems and limited demand are related to low completion rates of public projects. Completion of public projects is the major problem as they are not successful and fall out of use at an alarming rate. The study examined the influence of project life cycle management on completion of public projects in Kenya. The study adopted a descriptive research approach which involved target population of 131 projects and a census survey design was used to collect primary data. The data was analyzed by quantitative methods with the help of Statistical Package for Social Sciences (SPSS) version 22. It is notable that there exists a strong positive relationship between the independent variables and dependent variable as shown by R value (0.898). Additionally, project planning, execution and closure phases in project life cycle management are positively correlated. The study recommends that during the project initiation phase there is need to carry out problem identification, funding and costing to increase the completion of public projects. In addition, there study recommends that during the project planning phase, there is need to have resource plan, stakeholder plan. The study established that time, cost and quality management influence completion of public projects. Finally, the study established to a great extent that the communication reporting through documentation of project activities, release of projects resources and decision making on planning, promotion and training of the project beneficiaries. A comparative study should be carried out to compare whether the findings also apply for projects in other organizations in order to validate whether the findings can be generalized in Kenya. Additionally, the study did not tie the drivers as the only determinants of project life cycle management. Thus, there is need to undertake further research to examine other factors which could influence completion of public projects in Kenya.

Key Words: Project Initiation, Project Planning, Project Execution, Project Closure, Public Projects


Full Text:

PDF

References


Agle, B. R., R. K. Mitchell & J.- A. Sonnenfeld: 2008, 'Who Matters to CEOs? An Investigation of Stakeholder Attributes and Salience, Corporate performance, and CEO Values', Academy of Management Journal 42, 507-525.

Ahsan, K., Gunawan, I., 2010. Analysis of cost and schedule performance of international development projects. International Journal of Project Management 28 (1), 68–78. ares552e.htm. Last visited December, 2006.

Atrill, P. (2006). Financial Management for Decision Makers, (4th ed.). London: Prentice Hall.

Beach, S. (2009). Who or what decides how stakeholders are optimally engaged by governance networks delivering public outcomes? Australian Centre for Business Research; QUT Business School; School of Management.

Belassi W. and Tukel O. (2002). A new framework for determining critical Success/failure factor in Projects. International Journal for Project Management.

Bordens, K. S., and Abbott, B.B. (2008). Research design methods: A process approaches (7thed.). New York, NY: McGraw-Hill.

Burke, R. (2004). Project Management Planning and Control Techniques. 4th edition, New Delhi India: Pearson Education.

Callahan, M. T., D. G. Quackenbush, and J. E. Rowings, (2006). “Construction Project scheduling”. USA: McGraw-Hill.

Chandran C. (2004). Research Methods: A qualitative Approach with Illustrations from Christian Ministries. Nairobi: Daystar University.

Chikati , J. (2009). Project Cycle Management: an Integrated Approach and Logical. Pearson. New Delhi.

Cooper D R, Schindler PS (2005). Business Research Methods. (8th ed.). Mc Graw-Hill, New Delhi, India.

Creswell, J. W. (2003).Research design: Quantitative, qualitative, and mixed methods approaches (2nd Ed.). Thousand Oaks, CA: Sage.

Creswell, J. W., (2002). Educational research: Planning, conducting, and evaluating quantitative and qualitative approaches to research. New Jersey: Merrill/Pearson Education.

Deloof, M. (2003). “Does Working Capital Management Affect Profitability of Belgian Firms?”Journal of Business Finance and Accounting, Vol. 30, No. 3 & 4, 573-587.

Dennis Lock (2007). Project Management. Gower Publishing Limited, New Delhi.

Donaldson, S. I. (2001). Overcoming our negative reputation: Evaluation becomes known as a helping profession. American Journal of Evaluation, 22, 355-361.

Donaldson, T. and Preston, L. (1995). The Stakeholder Theory of the Corporation: Concepts, Evidence, and Implications. Academy of Management Review, v 20, n 1, pp65-91.

Freeman, R.E. (2004). Strategic Management: A stakeholder approach. Boston: Pitman.

Freeman, R.E., and Phillips, R. A. (2002). Business Ethics Quarterly, 12(3), 331-349.

Goldratt E. and Cox J., (2002). The Goal: A process of ongoing improvement. (Revised Ed.). Croton-on-Hudson. North River Press.

Goldratt, E. M. (2006). Critical chain. The North River Press, Great Barrington, U.S.

Government of Kenya (2009). Ministry of Planning and National Development: The National census. Nairobi: Government Printer.

Government Press (2005). Ministry of Planning: Millennium Development Goal 7.

Harold, K. (2009). Project Management: A systems Approach to Planning, Scheduling and Controlling (8th ed.). Wiley Publishing: NY.

Harvey, Maylor (2010). Project Management (4th ed.). Englewood Cliffs: Prentice Hall.

Heldman, K. 2011. Project management jumpstart. 3rd ed. Hoboken, NJ: Wiley

Herman, S .John, M. and Nicholas (2011). Project Management for Business, Engineering and Technology, Principles and Practice, 3rd Edition

Hitesh, B. (2009). Marketing strategy management. (2nd ed.). New Delhi India: Response Books.

Hoard, C.A. 2003. Hierarchy of skills: laying a foundation for PM Maturity. [online]. Available from: http://www.gantthead.com/content/articles/176281.cfm>. [Accessed 12 April 2011].

Hunkeler D and Rebitzer G (2005). The Future of Life Cycle Assessment. The International Journal of Life Cycle Assessment 10(5) 305-308.

IFAD ( 2006); Completion of rural development projects Best practicesand lessons learned by IFAD in Asia India Case Study North Eastern Region Community Resource Management Project for Upland Areas

Jack R. Meredith and Samuel J.Mantel (2010). Project Management : A Managerial Approach. (8th ed.). New Delhi.

James P. Lewis (2005). Project Planning Scheduling and Control. USA. Mc Graw Hill.

Jankowicz, A.D., (2005). Business Research Projects, (4thed.). Luton.

JenniferR. McConville(2006):Applying Life Cycle Thinking To International Water and Sanitation Development Projects:An Assessment Tool for Project Managers inSustainable Development work

Johnson, G. & Scholes, K., (2003). Exploring Corporate Strategy. (7th Edition). New Delhi: Prentice Hall

Joseph, K, M. (2013). Effect of fund management practices on the financial performance of cdf funded water projects in Kenya a case of Moloconstituency ,NakuruCounty, Kenya. Available at http://ir.kabarak.ac.ke/bitstream/handle/123456789/179

Karl, M. (2000). Monitoring and evaluation stakeholder participation in Agriculture and rural development projects. A literature review. Sustainable Development(SD) Food and Agriculture Foundation of the United Nations (FAO).Available at http//www.fao.org./sd/PPdirect/PPre0074.htm

Kerzner, H. (2003). Project Management: A Systems Approach to Planning, Scheduling, and Controlling, New York: Wiley, p.45.

Kitui County Integrated Development Plan (2013- 2017). Planning for sustainable Socio-Economic Growth and Development

Kliem, R.L. 2008. Effective communications for project management. Boca Raton: Auerbach/Taylor & Francis.

Klöpffer W (2003). Life-Cycle Based Methods for Sustainable Product Development. The International Journal of Life Cycle Assessment 8 (3) 157-159. Labuschagne

Knipe, A., Van der Waldt, G., Van Niekerk, D., Burger, D. & Nell, K. 2002. Project management for success. Sandown: Heinemann.

Komalawati (2008). Participation and Project Susutainability: Participatory Intergrated Development in Rain-fed (PIDRA) Projects in East Java -Indonesia

Kombo P.O. (2006). Project and Writing: An Introduction. Pauline’s Publications Africa.

Kothari, C.R. (2004). Research methodology: methods and techniques. New Delhi: New Age International.

Krejcie and Morgan (2006). In their article "Determining Sample Size for Research Activities" (Educational and Psychological Measurement, pp. 607-610).

Kwak, Y.H., 2002. Critical success factors in international development project management. CIB 10th International Symposium Construction Innovation & Global Competitiveness. Cincinnati, Ohio. 9–13 septembre

Lamberson, M. (2005). Changes in Working Capital of Small Firms in Relation to Changes in Economic Activity, Retrieved from http://www.AJBonline.com on 17th August 2014.

Laufer, A., H. Woodward., and G. A. Howell. (1999). Managing the decision making process during project planning. Journal of Management in Engineering, 15(2):79-84.

Lavagnon A. Ika a,, Amadou Diallo b, Denis Thuillier ( 2011) Critical success factors for World Bank projects: An empirical investigation International Journal of Project Management pg105- 106 Ste Catherine Est, C.P. 6192, Montréal, Québec, Canada H3C 4R2

Lawther P., Light B and Gibson N. (2000). "A Critical Success factors model for projects rise resources planning implementation" Proceedings (8th Ed.). European Conference onInformation Systems.

Lewis R. Ireland (2006). Project Management. McGraw-Hill Professional: UK.

Loker, W.M. (2000). Sowing discord, planting doubts: Rhetoric and reality in art environment and development project in Honduras. Human Organization, 59(3): 300-310.

Love, H., Mackinnon, D., Cumbers, A, Chapman, K.(2005),Learning, Innovation and regional development ;a critical appraisal of recent debates, Progress in Human Geography, Vol 26.No. 3, pp.293-311.

Makgoshi and Maliwichi (2010). Completion of Poverty Eradication Projects in rural Communities. Acts Publishing: Kenya.

Malladi, S. (2007). Enhancing project performance and productivity. Addressing it in project management and beyond Pm tips and techniques .PM tips and techniques.pm world today,9(7)

Matsumura,K. (2008). Causes of Poor Performance in World Bank Water and Sanitation Projects.

Maylor, C. and Vessey, I. (1999). "TRP Implementation approaches towards a consistency framework". New York

Maylor, H., Brady, T., Cooke Davis, T. and Hodgson, D. (2006). “From projectification to programmification, International Journal of Project Management, Vol. 24 No 8.

Mbachu and Nkondo (2007). ISK Sue Arrow smith and Arwel Davies, eds. London: Kluwer Law International.

Meredith J, R (2006) Project Management. A Managerial Approach, John Wiley & Sons, IncNewyork.

Morardet ,S. Merrey, J. Seshoka& H. Sally (2005). Improving Irrigation Project, Planning and Implementation in Sub-sahara Africa: Diagnosis and Recommendations.

Mugambi, D.K, (2005). Challenges of Project Implementation of Community based Goat breeding Projects. A case study of Meru. Unpublished MBA thesis, Kenyatta University.

Mugenda O,&Mugenda A. (2003). Research methods: Quantitative and qualitative approaches. Nairobi; Laba Graphics Services.

Mugenda, A., and Mugenda, O. (2003). Research methods; quantitative and qualitative approaches. Africa Center for Technology (ACTS), Nairobi Kenya.

Mugure ,F.M. (2012). Influence of community participation on the performance of Kiserian dam water projectKajiadocounty, Kenya.

Mwangi, K. (2005). Efficiency and efficacy of Kenya’s Constituency Development Fund: Theory and evidence. Working Paper Number 2005 – 42, Department of Economics, University ofConnecticut, U.S.A

Nosike, A.F (2005). Women Leadership and the Future. New Nigeria, July 22.

Nyaguthii E. and Oyugi L. A. (2013). Influence of community participation on successful implementation of constituency development fund projects in Kenya: a case study of Mwea Constituency; Available at: http://www.ijern.com/journal/August-2013/49.pdf

Ochelle (2009); Factors influencing completion of community water projects in Kenya; A case of community water Mulala division, Makueni County, University of Nairobi

Ochieng et al, (2012)Effectiveness of Monitoring and Evaluation of CDF Projects in Kenya. A Case of Ainamoi Constituency.International Journal of Arts and Commerce Vol. 1 No. 6 November 2012

Padachi, K. (2006). “Trends in Working Capital Management and its Effect on Firms’Performance: An Analysis of Mauritian Small Manufacturing Firms”. International Review of Business Research Papers, Vol. 2, No. 2, pp. 45-58

Patton, M.Q. (2002). Qualitative Research and Evaluation Methods. Thousand Oaks, California: Sage.

Paul K.Ngugi (2008). Planning Of Geothermal Projects: A Case Study on Kenya, Papers and Presentation s at “Short Course III on Surface Exploration for Geothermal Resources” Organized by UNU-GTP and KenGen in Naivasha Kenya

Pearson Education Limited, 2009. Code of Practice for Project Management for Construction and Development, Eight Edition, Edingurgh Gate, Harlow, England, 217pp

Phinney M. (2007). Project Management. A system approach to planning, scheduling and controlling (8thed.). Harold Kerzner, John Wiley & sons. New York.

Project Management Institute (PMI) (2008). A guide to the Project management body of knowledge (PMBOK® Guide) (4th Ed.). Newtown Square, PA, USA: Project Management Institute(PMI).

Project Management Institute (PMI). (2012). A guide to the Project management body of knowledge (PMBOK® Guide) (5th Ed.). Newtown Square, PA, USA: Project Management Institute (PMI).

Ravallion, M. (2005). Evaluating anti-poverty programmes. In T. P. Schultz & J. Strauss (Eds.), Development Research Group, World Bank and Handbook of Development Economics, 4, Amsterdam, North-Holland.

Repared (2009). The Project Management Handbook (Regional Partnership for Resource Development) Nairobi.

Rogers, P. (2009). Matching Impact Evaluation Design to the Nature of the Intervention and the purpose of the Evaluation in Designing impact evaluations: different perspectives. 3ie Working paper4.London: 3iE (www.3ieimpact.org/admin/pdfs_papers/50.pdf).64.

Rono, K.P and Aboud, A. A. (2003). The role of popular participation and community work ethic in rural development: the case of Nandi District, Kenya; Journal of Social Development in Africa Vol 18 No 2 July 2003

Rossi, P. H., Lipsey, M. W., and Freeman, H. E. (2004). Evaluation: A systematic approach (7th Ed.). Thousand Oaks, CA: Sage.

Samuel and Tom (2010), Project Management from Design to Implementation, Richmond designers and Printers, Nairobi.

Scriven, M. (1998). Minimalist theory. UK.

Shapiro J. (2004). Monitoring and Evaluation. Johannesburg: CIVICUS66.

Sirota P. (2006). Political participation of the NGOS in Project implementation in Nepal. International journal of organisations.2 April 2003:140-150.

Thairu, R,W. (2014). Analysis of implementation of NGO Projects in Nairobi County.

Tim, H. (2008). Management Concepts and Practices, Fifth Edition. Englewood Cliffs: Prentice Hall

Trevor L. Young, (2008) Successful Project Management, the Sunday Times, 2nd Edition

UNDP (2002). Handbook on Monitoring and Evaluation for Results. New York: UNDP.

UNIDO(2013); Independent UNIDO Country Evaluation Republic of Kenya 2013

United Nations (2000). Millennium Development Goals http://www.un.org/millennium goals/, accessed June 24, 2006

United Nations, 2003.United Nations Millennium Declaration (A/55/L.2)[Online] Available at: http://www.un.org/millennium/declaration/

Wayne and Wittig(2002) Building value through Project implementation: A focus on A focus on Africa Three.

Weiss H. (2004). On Theory – Based Evaluation: Winning Friends and Influencing People Evaluation Exchange, 9(4): 2 -773.

Wil D. Verwey (1977). Riot Control Agents and Herbicides in War.BRILL.p. 99.ISBN 9028603360.

World Bank (2007) Project Performance: Project performance issues. Report v.washington.USA.

Wysocki, R.K. 2007. Effective Project management: traditional, adaptive, extreme. Indianapolis, IN.: Wiley.

Zulu and Chileshe (2008). Poor performance of Zambian Contractors. Institution of Structural Engineers magazine, UK, July Publication.




DOI: http://dx.doi.org/10.61426/sjbcm.v3i4.315

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 2 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 1 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
  Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
  Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.