DETERMINANTS OF COMPLETION OF HOUSING PROJECTS IN INFORMAL SETTLEMENTS IN NAIROBI CITY COUNTY, KENYA

AGNES MUENI MWINZI

Abstract


The purpose of the study was to establish the determinants of completion of housing projects in informal settlements in Nairobi City County, Kenya. The study targeted project managers involved in the implementation of the projects who provided pertinent information about the research problem. The 100 projects were targeted as per to the records available. Descriptive analysis such as frequencies, percentages were used to present quantitative data in form of tables. Data from questionnaire was coded and logged in the computer using Statistical Package for Social Science. The study further adopted a regression analysis to determine the relationship among the variables at 5% level of significance. It was notable that there exists  strong positive relationship between the indepedent variables and depedent variable as shown by R value (0.849). The coefficient of determination (R2) explains the extent to which changes in the dependent variable can be explained by the change in the independent variables or the percentage of variation in the dependent variable and the four independent variables that were studied explain 72.10% of the completion of housing projects in informal settlements as represented by the R2. This therefore means that other factors not studied in this research contributed 27.90% of the completion of housing projects in informal settlements. This implies that these variables are very significant therefore need to be considered in any effort to boost completion of housing projects in informal settlements in Kenya. The study therefore identified variables as critical determinants of completion of housing projects in informal settlements. The study recommended that there is need to allow the project team to have sense of belonging in the management of the affairs in the projects. They can carry out higher responsibilities with other leaders with little supervision. These projects should not lack support from the key and primary stakeholders and beneficiaries. Stakeholders involvement makes everyone feel part and parcel of the project. The organizations need to have decision making process; the various types of risks have to be identified ex ante as far as possible. The organizations should have adequate risk identification mechanisms such as formulation of adequate. There should have risk identification strategy which is the basis for analysis and control of project activities.

Key Words: Risk Management, Project Resources, Stakeholder Involvement, Project Leadership, Housing Projects 


Full Text:

PDF

References


Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of delay in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831-841.

Adamu, K. J., Dzasu, W. E., Haruna, A., & Balla, S. K. (2011). Labor productivity constraints in the Nigerian construction industry. Continental Journal of Environmental Design and Management, 1(2), 9-13.

Aiyetan, A., Smallwood, J., & Shakantu, W. (2011). A systems thinking approach to eliminate delays on building construction projects in South Africa.Acta Structilia, 18(2), 19-39.

Akinsiku, O., Akintola, A., Ameh, O., & Ige, A. (2014). Contributions of Construction Project Team to Cost Overruns: The Contractors’ Perspective. In Construction Research Congress 2014: Construction in a Global Network (pp. 1528-1536).

Alaghbari, W. E., Razali A. Kadir, M., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management, 14(2), 192-206.

Al‐Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1), 3-23.

Alojairi, A. (2011). Project Management: A Socio-Technical Perspective.

Alshanbari, H. (2010). Impact of Pre-Construction Project Planning on Cost Savings (Doctoral dissertation, University of Florida).

Ameh, O. J., Soyingbe, A. A., & Odusami, K. T. (2010). Significant factors causing cost overruns in telecommunication projects in Nigeria. Journal of Construction in Developing Countries, 15(2), 49-67.

Andawei, M. E. M.(2014) Environmental Friendliness of Project Cost Management Process in Nigeria: The Role of the Quantity Surveyor.

Arogo, G. M. (2015). Factors influencing completion of community-initiated projects: the case of Eldoret town, Uasin Gishu county, Kenya (Doctoral dissertation, University of Nairobi).

Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International journal of project management, 24(4), 349-357.

Auma, E. (2014). Factors Affecting the Performance of Construction Projects in Kenya: A Survey of Low-Rise Buildings in Nairobi Central Business District. The International Journal of Business & Management,2(12), 115.

Barasa, J. A. (2014). Influence of board of managements’ contribution to development of public secondary schools in Nyamira north district, Nyamira county, Kenya (Doctoral dissertation, University of Nairobi).

Brown, A. D., & Phua, F. T. (2011). Subjectively construed identities and discourse: towards a research agenda for construction management. Construction Management and Economics, 29(1), 83-95.

Standard, A. (2011). Guide to the Project Management Body of Knowledge (PMBOK (R) Guide)–. In Project Management Institute.

Chavada, R., Dawood, N. N., & Kassem, M. (2012). Construction workspace management: the development and application of a novel nD planning approach and tool. Journal of Information Technology in Construction.

Chen, W. T., & Huang, Y. H. (2006). Approximately predicting the cost and duration of school reconstruction projects in Taiwan. Construction management and Economics, 24(12), 1231-1239.

Chigara, B., & Mangore, E. (2012). An analysis of the implications of resources management on building projects performance in Harare and Bulawayo. International Journal of Marketing and Technology, 2(9), 144.

Chigara, B., Moyo, T., & Mudzengerere, F. H. (2013). An Analysis of Cost Management Strategies Employed By Building Contractors on Projects in Zimbabwe. International Journal of Sustainable Construction Engineering and Technology, 4(2), 1-13.

Chirisa, I. (2014). Building and urban planning in Zimbabwe with special reference to Harare: Putting needs, costs and sustainability in focus.

Darrington, J. W., & Howell, G. A. (2010). An optimized project requires optimized incentives. In Proc. of the 18th Ann. Meeting of the IGLC.

Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479-489.

Durdyev, S., Ismail, S., & Bakar, N. A. (2013). Construction productivity in Turkmenistan: Survey of the constraining factors. International Journal of e-Education, e-Business, e-Management and e-Learning, 3(1), 18.

El-Behary, H. (2013). High prices cripple the construction sector. Daily News Egypt (Egypt) the Gale Group, Farmington Hills, Michigan.

El-Gohary, K. M., & Aziz, R. F. (2013). Factors influencing construction labor productivity in Egypt. Journal of Management in Engineering, 30(1), 1-9.

Enshassi, A., Mohamed, S., Mustafa, Z. A., & Mayer, P. E. (2007). Factors affecting labour productivity in building projects in the Gaza Strip. Journal of Civil Engineering and Management, 13(4), 245-254.

Faridi, A. S., & El‐Sayegh, S. M. (2009). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167-1176.

Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. International Journal of project management, 21(5), 321-326.

Fugar, F. D., & Agyakwah-Baah, A. B. (2010). Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, The, 10(1/2), 128.

Githui, D. M. (2012). Ethical issues in the construction industry in Kenya: A critical analysis of the professional conduct in engineering technology management.

Gundecha, M. (2012). Study of factors affecting labor productivity at a building construction project in the usa: web survey (Doctoral dissertation, North Dakota State University).

Hoffman, G. J., Thal Jr, A. E., Webb, T. S., & Weir, J. D. (2007). Estimating performance time for construction projects. Journal of Management in Engineering, 23(4), 193-199.

Hwang, B. G., Zhao, X., & Ng, S. Y. (2013). Identifying the critical factors affecting schedule performance of public housing projects. Habitat International, 38, 214-221.

Jarkas, A. M., & Bitar, C. G. (2011). Factors affecting construction labor productivity in Kuwait. Journal of Construction Engineering and Management, 138(7), 811-820.

Jerven, M. (2013). Poor numbers: how we are misled by African development statistics and what to do about it. Cornell University Press.

Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27(5), 522-531.

Kalsum, U., Hanid, M., Zakaria, N., Yahya, Z., & Lia, P. C. (2010). Assessing the performance of construction workers in Peninsula Malaysia. International Journal of Engineering and Technology, 7(2), 47-60.

Kikwasi, G. (2013, February). Causes and effects of delays and disruptions in construction projects in Tanzania. In Australasian Journal of Construction Economics and Building-Conference Series (Vol. 1, No. 2, pp. 52-59).

Koontz, H. (2010). Essentials of management. Tata McGraw-Hill Education.

Kothari, C. R. (2004). Research methodology: Methods and techniques. New Age International.

Koushki, P. A., Al‐Rashid, K., & Kartam, N. (2005). Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 23(3), 285-294.

Langat, D. K. (2015). Factors influencing completion of construction projects in public secondary schools in Bomet east sub-county, Bomet county, Kenya (Doctoral dissertation, University of Nairobi).

Le-Hoai, L., Dai Lee, Y., & Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE journal of civil engineering, 12(6), 367-377.

Lo, T. Y., Fung, I. W., & Tung, K. C. (2006). Construction delays in Hong Kong civil engineering projects. Journal of Construction Engineering and Management, 132(6), 636-649.

Love, P. E., Sing, C. P., Wang, X., Edwards, D. J., & Odeyinka, H. (2013). Probability distribution fitting of schedule overruns in construction projects. Journal of the Operational Research Society, 64(8), 1231-1247.

Mahdavinejad, M., & Molaee, M. (2011). The result of delayed projects on publics' satisfaction in Tehran. In 2nd International Conference on Construction and Project Management IPEDR. Singapore (pp. 16-18).

Makulsawatudom, A., Emsley, M., & Sinthawanarong, K. (2004). Critical factors influencing construction productivity in Thailand. The journal of KMITNB, 14(3), 1-6.

Mantel, S. J. (2011). Project management in practice. Wiley,

Marzouk, M. M., & El-Rasas, T. I. (2014). Analyzing delay causes in Egyptian construction projects. Journal of advanced research, 5(1), 49-55.

Masieka, Z. J. (2012). Factors influencing implementation of Adventist Development Relief Agency's educational projects in Nyamira County, Kenya (Doctoral dissertation, University of Nairobi, Kenya).

Mayavi, P. M. (2015). Influence of risk management process on the quality of construction of petrol station projects in Kenya: A case of petrol stations in Westlands constituency, Nairobi county, Kenya (Doctoral dissertation, University of Nairobi).

McLeod, L., Doolin, B., & MacDonell, S. G. (2012). A perspective‐based understanding of project success. Project Management Journal, 43(5), 68-86.

Moyo, T., Mangore, E., & Chigara, B. (2014). Work Measurement Techniques Utilized by The Building Industry in The Midlands Province Of Zimbabwe. International Journal of Sustainable Construction Engineering and Technology, 5(1), 42-52.

Muchungu, M. P. (2012). The contribution of human factors in the performance of construction projects in Kenya (Doctoral dissertation, University of Nairobi).

Mugenda,O.Mugenda. A.(2003). Research methods Quantitative and Qualitative Approaches. Nairobi: ACTS.

Muya, M., Kaliba, C., Sichombo, B., & Shakantu, W. (2013). Cost escalation, schedule overruns and quality shortfalls on construction projects: The case of Zambia. International Journal of Construction Management, 13(1), 53-68.

Ngacho, C., & Das, D. (2014). A performance evaluation framework of development projects: An empirical study of Constituency Development Fund (CDF) construction projects in Kenya. International Journal of Project Management, 32(3), 492-507.

Nyakazeya, P. (2012). Construction sector to grow. Financial Gazette, 22, 16.

Ochieng, E. G., & Price, A. D. F. (2010). Managing cross-cultural communication in multicultural construction project teams: The case of Kenya and UK. International Journal of Project Management, 28(5), 449-460.

Ochieng, F., & Ruth, T. (2013). Factors influencing management of CDF projects: A case of Ainamoi Constituency, Kericho County. International Journal of Science and Technology, 2(1), 1-15.

Ofori, G., & Lean, C. S. (2001). Factors influencing development of construction enterprises in Singapore. Construction Management & Economics, 19(2), 145-154.

Ogunsemi, D. R., & Jagboro, G. O. (2006). Time‐cost model for building projects in Nigeria. Construction Management and Economics, 24(3), 253-258.

Oino, P. G., Auya, S., & Luvega, C. (2014). Women Groups: A Pathway to Rural Development in Nyamusi Division, Nyamira County, Kenya. International Journal of Innovation and Scientific Research, 7(2), 111-120.

Olander, S., & Landin, A. (2005). Evaluation of stakeholder influence in the implementation of construction projects. International journal of project management, 23(4), 321-328.

Olaoluwa, O., & Adeyemi, A. Y. (2009). Effects of placing methods on concreting productivity. In Proceedings of The Botswana Institution of Engineers (BIE) Conference, Gaborone, Botswana (pp. 154-161).

Ondari, P. O., & Gekara, J. M. (2013). Factors influencing successful completion of roads projects in Kenya. International Journal of Social Sciences and Entrepreneurship, 1(6), 26-48.

Ondego, B., & Moturi, C. (2016). Evaluation of the Implementation of the e-Citizen in Kenya. Evaluation, 10(4).

Rahaman, M. M. (2011). Access to financing and firm growth. Journal of Banking & Finance, 35(3), 709–723.

Ringera, J. K. (2015). Factors influencing completion of selected Kenya police service housing projects in central Kenya (Doctoral dissertation, University of Nairobi).

Saka, N., & Lowe, J. (2010). An assessment of comovement between foreign direct investment (FDI) and South African construction sector (SACS) output. In Procs 26th Annual ARCOM Conference. Association of Researchers in Construction Management (pp. 83-92).

Sambasivan, M., & Soon, Y. W. (2010). Causes and effects of delays in Malaysian construction industry. International Journal of project management, 25(5), 517-526.

Shehu, Z., & Akintoye, A. (2010). Major challenges to the successful implementation and practice of programme management in the construction environment: A critical analysis. International Journal of Project Management, 28(1), 26-39.

Siemens, G. (2014). Connectivism: A learning theory for the digital age.

Soham, M., & Rajiv, B. (2013). Critical factors affecting labour productivity in construction projects: case study of south gujarat region of india. International Journal of Engineering and Advanced Technology, 2(4), 583-591.

Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), 665-674.

Tonnquist, B. (2008). Projektledning. Bonnier utbildning.

Turner, J. R. (Ed.). (2013). Contracting for project management. Gower Publishing, Ltd.

Winch, G. M. (2010). Managing construction projects. John Wiley & Sons.

Xia, B., & Chan, A. P. (2012). Measuring complexity for building projects: a Delphi study. Engineering, Construction and Architectural Management,19(1), 7-24

Yin, R. K. (2010b). Qualitative research from start to finish. Guilford Press.

Zami, M. S. (2011). Potentialities of contemporary earth construction addressing urban housing crisis in Africa–A lesson from Zimbabwe. Plenary Paper Session I: Water, 66.

Zint, M., & Montgomery, N. (2012). Evaluation: What is it and why do it. available online on http://meera. snre. umich. edu/plan-an-evaluation/evaluation-what-is-it-and-why-do-itc last accessed 27th Jan.

Zulu, S., & Chileshe, N. (2010). Service quality of building maintenance contractors in Zambia: a pilot study. International Journal of Construction Management, 10(3), 63-81.




DOI: http://dx.doi.org/10.61426/sjbcm.v5i2.737

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 2 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 1 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
  Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
  Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.