DETERMINANTS OF COMPLETION OF BUILDING CONSTRUCTION PROJECTS IN KENYA: A CASE STUDY OF NAIROBI COUNTY

ATHUMAN ODUKI SIATI, DR. JOYCE NZULWA (Ph.D), RONALD KWENA

Abstract


The study was conducted to evaluate the components prompting the completion of building construction projects in Kenya: a case study of Nairobi County. It had four specific objectives which were; to determine how stakeholders, project financing, project planning and how project supervision impact on the completion of building construction projects in Nairobi County. The study assumed a descriptive survey research design in which 68 randomly selected respondents; Architects, Quantity surveyors, Developers; Project managers and Civil/ Structural engineers to which questionnaires were administered. Data was collected, examined and checked for completeness and clarity, coded and logged in the computer and analyzed using SPSS. Regression and correlations tables were used to present the findings. Results went through a critical assessment of each response and examined using thematic interpretation in accordance with the main objectives of the study and thereafter presented in narrative excerpts within the report. The study established that stakeholder involvement played a critical role in determining the completion of building Construction Projects. Most respondents had a reservation about the Project manager considering stakeholders’ interests whereas others disagreeing with the fact that financial disclosure was a common occurrence in projects. It was however recommended that in order to achieve completion of building construction projects, it was important for the project manager to ensure that all stakeholders in the project were involved in the right stages and their views and interests were taken into account. They should be sensitized on the likely delays which could influence the delay and eventually cost of the project. 

Key words: Stake Holder Involvement, Project Financing, Project Planning, Project Supervision Completion of Building Construction Projects.

CITATION: Siati, A. O., Nzulwa, J., & Kwena, R. (2019). Determinants of completion of building construction projects in Kenya: A case study of Nairobi County. The Strategic Journal of Business & Change Management, 6 (2), 702 –716.


Full Text:

PDF

References


Ahmed, S. M., Azhar, S., Castillo, M., Kappagantulla, P.(2002).Construction delays in Florida: An Empirical Study. Florida: State of Florida Department of Community Affairs.

Auma, E. (2014). Factors affecting the performance of construction projects in Kenya: a survey of low-rise buildings in Nairobi Central Business District. The International Journal of Business & Management, 2(12), 115.

Assaf, S. A. and Al-Hejji, S. (2006). Causes of delay in large construction projects. International journal of project management, 24(4), 349-357.

Chan, M.M. and Kumaraswamy, D.W.M. (2002)Compressing construction durations: Lessons learned from Hong Kong building projects Int.J Proj. Manage. 20 (1) (2002), pp. 23–35.

Chai, A. H. R. (2016).Competencies of Construction Manager (Doctoral dissertation, UTAR).

El-Gohary, N. M., Osman, H., and El-Diraby, T. E. (2006).Stakeholder management for public private partnerships. International Journal of Project Management, 24(7), 595-604.

Gaba, G. (2013). The impact of project delivery systems, cost minimizations and project control on construction project success. Evidence from Ghana (Master‘s thesis). University College London, London, United Kingdom.

Goldratt, E. M. and Cox, J. (2016). The goal: a process of ongoing improvement. Routledge.

Government of Kenya (2008).Kenya Poverty Integrated Assessment Report. Nairobi: Government Printer.

Government of Kenya, (2010).The 2009 Kenya Population and Housing Census: Counting Our People for the Implementation of Vision 2030. Government Printer: Nairobi

Hill, R. (1998). What sample size is “enough” in internet survey research. Interpersonal Computing and Technology: An electronic journal for the 21st century, 6(3-4), 1-10.

Iyer, K. C. and Jha, K. N. (2005). Factors affecting cost performance: evidence from Indian construction projects. International journal of project management, 23(4), 283-295.

TalukhabaA, A, (2009),An Investigation into Factors Causing Project Delays in Kenya. Case Study of High-Rise Buildings in Nairobi, unpublished PHD Thesis, University of Nairobi.

Kamau, C. G., and Mohamed, H. B. (2018). Efficacy of Monitoring and Evaluation Function in Achieving Project Success in Kenya: A Survey of County Government’s Projects. IJAME.

Kikwasi, G.J. (2012) ‘Causes and effects of delays and disruptions in construction projects in Tanzania’, Australasian Journal of Construction Economics and Building, Conference Series, 1 (2) 52-59.

Lam, E. W., Chan, A. P. and Chan, D. W. (2008). Determinants of successful design-build projects. Journal of Construction Engineering and management, 134(5), 333-341.

Mugenda A. and Mugenda, O., (2008).Research Methods: Quantitative and Qualitative Approaches. Acts Press, Nairobi.

Nyambura, W. B., PROJECTPLANNING, I. (2015). Factors Influencing Completion Of Building Projects In Kenya, Ministry Of Land, Housing And Urban Development, Nairobi County.

Ogunsemi, D. R., and Jagboro, G. O. (2006). Time‐cost model for building projects in Nigeria. Construction Management and Economics, 24(3), 253-258

Rosazuwad, M., (2010).The Factors and Effects of Delay InGovernment Construction Project (Case Study InUganda)-Retrievedon6.01.2

Waihenya J., (2011).Identifying Causes of Cost Overruns in Traditional Contracts in Kenya, MA Thesis, University of Nairobi

Wideman R. M. (1986). "The PMBOK Report -- PMI Body of Knowledge Standard," Project Management Journal, Vol. 17, No. 3, August 1986.

Zhang, X. and AbouRizk, S. M. (2006). Determining a reasonable concession period for private sector provision of public works and service. Canadian Journal of Civil Engineering, 33(5), 622-631.




DOI: http://dx.doi.org/10.61426/sjbcm.v6i2.1137

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 4 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 3 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
 Vol 11, No 2 [2024] Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
 Vol 11, No 1 [2024] Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.