EFFECT OF EXTERNAL FACTORS ON COMPLETION OF CONSTRUCTION PROJECTS IN KENYA: A CASE STUDY OF THE DEPARTMENT OF HEALTH, MAKUENI COUNTY, KENYA

ANTONY MOGONDO KIBORE, LUCY KIRIMA, PhD, JOE KAMAU, PhD

Abstract


The completion of construction projects is dependent on a project cycle that is seamless to ensure reliability. External factors in the study included political factors, socio-economic factors and technological factors. The objectives were the effect of political, socio-economic and technological factors on the completion of construction projects in the department of health, Makueni County, Kenya. The theoretical framework included the theory of constraints and the resource dependency theory. The target population was the 238 projects in health facilities in Makueni county initiated between financial year 2021/2022 and 2022/2023. The respondents were the facility managers who are also the Health Facility Project Management Committee secretaries. Cross sectional Descriptive study approach was utilized in this study. A stratified sampling approach was used. The sample size was 150 projects. Primary data was gathered using a structured questionnaire. Chi-square test was used to determine association between variables. Multivariate logistic regression analysis was used to determine the effect of significant external factors on completion of construction projects. Statistical significance was assumed at P<0.05. Majority of the study participants were aged between 31.0 and 40.0 years old (56.0%), were nurses (77.3%), had managed their facility for over 5 years (74.7%) and were working in a Dispensary (77.3%).  The male and female participant ratio was 1:1. There was less likelihood of the projects being completed in the presence of political involvement, transition in leadership, and contract payment (OR 0.1, 0.7 and 0.3 respectively). Political involvement and contract payment were found to be statistically significant when it came to project not being completed (p 0.001 and p 0.004 respectively). Raw material availability was significantly associated with completion of projects (p 0.03). Multivariate analysis showed increased odds of completing construction projects from 2.7 to 5.3 times when raw materials were available. The study concluded that political factors and socio-economic factors significantly affect completion of construction projects. The study recommends that key stakeholders involved in the construction management process such as politicians be taken through monitoring and evaluation training to ensure that projects are well management and all risks averted. The researcher recommends a comparative study on the effect of technological factors on completion of construction projects.

Keywords: Health Facility, Project, External, Political, Socio-economic, Technological

CITATION: Kibore, A., Kirima, L., & Kamau, J. (2024). Effect of external factors on completion of construction projects in Kenya: A case study of the department of health, Makueni County, Kenya. The Strategic Journal of Business & Change Management, 11 (2), 758 – 766. http://dx.doi.org/10.61426/sjbcm.v11i2.2934


Full Text:

PDF

References


Abeysinghe, N., & Jayathilaka, R. (2022). Factors influencing the timely completion of construction projects in Sri Lanka. PLOS ONE, 17(12), e0278318. https://doi.org/10.1371/journal.pone.0278318

Aiyetan, A. O., & Das, D. K. (2022). Factors and Strategies for Improving Construction Management on Sites in Mega-Projects in South Africa: An Explorative Survey. Infrastructures, 7(2), Article 2. https://doi.org/10.3390/infrastructures7020019

Behncke, S. (2022). Effects of Macroprudential Policies on Bank Lending and Credit Risks. Journal of Financial Services Research. https://doi.org/10.1007/s10693-022-00378-z

Beyene, S. D. (2023). The impact of food insecurity on health outcomes: Empirical evidence from sub-Saharan African countries. BMC Public Health, 23(1), 338. https://doi.org/10.1186/s12889-023-15244-3

Bucăţa, G., & Rizescu, M. (2017). The Role of Communication in Enhancing Work Effectiveness of an Organization. Land Forces Academy Review, 22. https://doi.org/10.1515/raft-2017-0008

Chang, T., Deng, X., Hwang, B.-G., & Zhao, X. (2018). Political Risk Paths in International Construction Projects: Case Study from Chinese Construction Enterprises. Advances in Civil Engineering, 2018, e6939828. https://doi.org/10.1155/2018/6939828

Chen, X., Li, H., Lucero-Prisno, D. E., Abdullah, A. S., Huang, J., Laurence, C., Liang, X., Ma, Z., Mao, Z., Ren, R., Wu, S., Wang, N., Wang, P., Wang, T., Yan, H., & Zou, Y. (2020). What is global health? Key concepts and clarification of misperceptions. Global Health Research and Policy, 5, 14. https://doi.org/10.1186/s41256-020-00142-7

Gashaahun, A. (2020). Causes and Effects of Delay on African Construction Projects: A State of the Art Review. 12, 41–53. https://doi.org/10.7176/CER/12-5-04

Hanif, M., & Khattak, S. (2017, February 21). Assesment of Economic Factors for Sustainable Construction Industry.

Kairu, A., Orangi, S., Mbuthia, B., Ondera, J., Ravishankar, N., & Barasa, E. (2021). Examining health facility financing in Kenya in the context of devolution. BMC Health Services Research, 21(1), 1086. https://doi.org/10.1186/s12913-021-07123-7

Khahro, S. H., Memon, A. H., Memon, N. A., Memon, Z. A., & Naresh, R. (2023). Influence of Social and Economic Factors on Construction Project Performance in Pakistan. Sustainability, 15(3), Article 3. https://doi.org/10.3390/su15032469

Kihoro, M. W. (2015). FACTORS AFFECTING PERFORMANCE OF PROJECTS IN THE CONSTRUCTION INDUSTRY IN KENYA: A SURVEY OF GATED COMMUNITIES INNAIROBI COUNTY. Strategic Journal of Business & Change Management, 2(2), Article 2. https://strategicjournals.com/index.php/journal/article/view/121

Mavetera, N., Sekhabisa, K., Mavetera, C., & Choga, I. (2015). Factors influencing success of construction projects by emerging contractors in south Africa: A case of Mahikeng area. Corporate Ownership and Control, 13, 820–843. https://doi.org/10.22495/cocv13i1c9p6

Moses, M. W., Korir, J., Zeng, W., Musiega, A., Oyasi, J., Lu, R., Chuma, J., & Di Giorgio, L. (2021). Performance assessment of the county healthcare systems in Kenya: A mixed-methods analysis. BMJ Global Health, 6(6), e004707. https://doi.org/10.1136/bmjgh-2020-004707




DOI: http://dx.doi.org/10.61426/sjbcm.v11i2.2934

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 4 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 3 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
 Vol 11, No 2 [2024] Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
 Vol 11, No 1 [2024] Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.