STAKEHOLDER MANAGEMENT AND IMPLEMENTATION OF ROADS CONSTRUCTION PROJECTS BY KENYA URBAN ROADS AUTHORITY IN NAIROBI CITY COUNTY, KENYA

DAMARIS NJERI KOIGI NGUGI, LYDIA GACHENGO, PhD

Abstract


This study sought to investigate the influence of stakeholder management on implementation of roads construction projects by Kenya Urban Roads Authority in Nairobi City County, Kenya. The study was guided by stakeholder theory and systems theory. This study used descriptive research design. The target population in this study was 10 road projects by KURA from the year 2018 to 2022. The target respondents were 75 respondents working with KURA. The study used questionnaire to collect data of the study. Questionnaires were piloted to 8 respondents working with Kenya National Highway Authority. Quantitative data was analyzed using descriptive statistics such as mean and standard deviation. In order to test the relationship between variables and the extent to which they are influence each other inferential statistics such as multiple regression analysis was used. The study examined that stakeholder communication (t=36.773, p<0.05), stakeholder participation (t=21.697, p<0.05), conflict management (t=6.336, p<0.05) and stakeholder analysis (t=11.579, p<0.05) had a positive significant influence on the implementation of roads construction projects by Kenya Urban Roads Authority in Nairobi City County, Kenya. The study concludes that engaging stakeholders in communication help to build trust and foster positive relationships between the Kenya Urban Roads Authority and the community. The stakeholder participation help identifies potential issues or challenges early on, allowing for timely adjustments and improvements to the project plan. Effective conflict management strategies are crucial to address and resolve these conflicts, ensuring the timely completion and quality of the roads construction projects. Stakeholder analysis enables the organization to improve on communication and collaboration which help prevent conflicts, delays, and cost overruns, ultimately leading to a more efficient and successful project delivery. The study recommended that the organization should keep the stakeholders informed about the progress of construction projects, address their concerns, and solicit their feedback. Kenya Urban Roads Authority should actively engage with stakeholders to ensure that the decision-making process is open and inclusive. Kenya Urban Roads Authority should establish clear communication channels between all stakeholders involved in the project, including government agencies, contractors, local communities, and other relevant parties. Kenya Urban Roads Authority should implement a comprehensive stakeholder engagement plan by involving all relevant parties, including local communities, government agencies, contractors, and other stakeholders. Kenya Urban Roads Authority should conduct stakeholder mapping, which involves creating a visual representation of the stakeholders and their relationships to the project.

Key Words: Stakeholder Communication, Stakeholder Participation, Conflict Management, Stakeholder Analysis

CITATION: Ngugi, D. N. K., & Gachengo, L. (2024). Stakeholder management and implementation of roads construction projects by Kenya Urban Roads Authority in Nairobi City County, Kenya. The Strategic Journal of Business & Change Management, 11 (2), 1328 – 1348. http://dx.doi.org/10.61426/sjbcm.v11i2.2992


Full Text:

PDF

References


Aaltonen, K. (2019). Project stakeholder analysis as an environmental interpretation process. International journal of project management, 29(2), 165-183

Ahiaga-Dagbui, D. D., Love, P. E., Smith, S. D., & Ackermann, F. (2019). Toward a systemic view to cost overrun causation in infrastructure projects: A review and implications for research. Project management journal, 48(2), 88-98

Awwad, R., Barakat, B., & Menassa, C. (2021). Understanding dispute resolution in the Middle East region from perspectives of different stakeholders. Journal of Management in Engineering, 32(6), 6 - 13.

Butt, A., Naaranoja, M., & Savolainen, J. (2016). Project change stakeholder communication. International Journal of Project Management, 34(8), 1579-1595

Buyukozkan, G., & Karabulut, Y. (2017). Energy project performance evaluation with sustainability perspective. Energy, 119, 549-560

Cao, Q., & Hoffman, J. J. (2021). A case study approach for developing a project performance evaluation system. International Journal of Project Management, 29(2), 155-164

Chinyavu, M. R. (2016). The influence of stakeholder participation on the performance of donor funded projects: A Case of Kinango Integrated Food Security and Livelihood Project (KIFSLP), Kwale County, Kenya (MAPPM Project, University of Nairobi).

Cullen, K., & Parker, D. W. (2015). Improving performance in project-based management: Synthesizing strategic theories. International Journal of Productivity and Performance Management, 64(5), 608-624.

DeCotiis, T. A., & Dyer, L. (2021). The dimensions and determinants of project performance. Industrial Marketing Management, 6(5), 370 – 378

Elias, A. A., Cavana, R. Y., & Jackson, L. S. (2018). Stakeholder analysis for R&D project management. R&D Management, 32(4), 301-310

Groom, D. R., & Solomon, M. (2019). Effect of Stakeholder Management on Project Performance in the case of GIZ, (Masters Project, Addis Ababa University)

Irfan, M., Thaheem, M. J., Gabriel, H. F., Malik, M. S. A., & Nasir, A. R. (2019). Effect of stakeholder’s conflicts management on project implementation: a tale of the construction industry. International Journal of Conflict Management, 30(4), 538-565.

Jackson, M. C. (2017). Social systems theory and practice: The need for a critical approach. International Journal of General System, 10(2-3), 135-151.

Kamau, E. M. (2019). Assessment of effect of stakeholders’ analysis and engagement on the performance of constituency development funded projects: A Survey of Vihiga County. International Journal of Recent Research in Social Sciences and Humanities, 5(1), 23 – 34

Khan, A., Waris, M., Panigrahi, S., Sajid, M. R., & Rana, F. (2021). Improving the performance of public sector infrastructure projects: Role of project governance and stakeholder management. Journal of Management in Engineering, 37(2), 3 - 12.

Kipkoech, A. (2022). Stakeholder participation and performance of Ngara Park Road Housing Project in Nairobi City County, Kenya (Master’s Project, Kenyatta University)

Mambwe, M., Mwanaumo, E. M., Nsefu, M. K., & Sakala, N. (2020). Impact of stakeholder management on performance of construction projects in Lusaka District. In Proceedings of the 2nd African International Conference on Industrial Engineering and Operations Management, Harare, Zimbabwe (pp. 7-10).

Mashali, A., Elbeltagi, E., Motawa, I., & Elshikh, M. (2022). Stakeholder management challenges in mega construction projects: critical success factors. Journal of Engineering, Design and Technology, 21(2), 358-375.

Mir, F. A., & Rezania, D. (2022). From interactive control to IT project performance: examining the mediating role of stakeholder analysis effectiveness. Journal of Accounting & Organizational Change, 18(5), 727-751.

Moulid, H. M., Muchelule, Y. W., & Wechuli, W. T. (2021). Influence of stakeholder’s management on the implementation of Coast Development Authority projects in Kenya. The Strategic Journal of Business & Change Management, 8(2), 158-177.

Mugata, R. J., & Yusuf, M. (2018). Effect of stakeholder analysis on performance of road construction projects in Elgeyo Marakwet County, Kenya. International Journal of Research in Education and Social Sciences, 2, 88-106.

Mwakajo, I. S., & Kidombo, H. J. (2017). Factors influencing project performance: A case of county road infrastructural projects in Manyatta Constituency, Embu County, Kenya. International Academic Journal of Information Sciences and Project Management, 2(2), 111-123.

Naqvi, I. H., & Aziz, S. (2018). The impact of stakeholder communication on project performance. African Journal of Business Management, 5(14), 5824.

Ndunda, A. N., Paul, S. N. & Mbura, L. K. (2017). Influence of stakeholder activities on implementation of rural road projects in Machakos County. International Academic Journal of Information Sciences and Project Management, 2(2), 1-20

Nguyen, T. S., Mohamed, S., & Panuwatwanich, K. (2018). Stakeholder Management in Complex Project: Review of Contemporary Literature. Journal of Engineering, Project & Production Management, 8(2), 56 – 69

Omondi, K., Kinoti, K. (2020). Stakeholder participation and performance of road construction projects in Kilifi County, Kenya. International Academic Journal of Information Sciences and Project Management, 3(6), 274-292

Onana, J. C. (2018). Factors affecting the performance of contractors on road projects supervised by national agency of public works in Gabon (Doctoral dissertation).

Oppong, G. D., Chan, A. P., & Dansoh, A. (2017). A review of stakeholder management performance attributes in construction projects. International journal of project management, 35(6), 1037-1051

Post, J. E., Preston, L. E., & Sachs, S. (2019). Managing the extended enterprise: The new stakeholder view. California management review, 45(1), 6-28

Rehman, A. U., Khan, A. M., & Khan, R. A. (2021). Measuring Training Effectiveness: A Case Study of Public Sector Project Management in Pakistan. Journal of Diversity Management, 6(1), 39 – 48

Rowlinson, S., & Cheung, Y. K. F. (2019). Stakeholder management through empowerment: modelling project success. Construction Management and Economics, 26(6), 611-623.

Saavedra, R., Earley, P. C., & Van Dyne, L. (2018). Complex interdependence in task-performing groups. Journal of applied psychology, 78(1), 61 – 75

Scholes, E., & James, D. (2018). Planning stakeholder communication. Journal of Communication Management, 2(3), 277-285.

Sewe, B. O. (2019). Stakeholder Conflict Management Strategies and Performance of Solid Waste Management Projects in Kisumu City, Kenya (Doctoral dissertation, University of Nairobi)

Soares, R. (2020). Stakeholder management and its influence on the performance of information technology projects (Doctoral dissertation, UNINOVE).

Sutterfield, J. S., Friday-Stroud, S. S., & Shivers-Blackwell, S. L. (2019). A case study of project and stakeholder management failures: lessons learned. Project Management Journal, 37(5), 26-35.

Yang, L., Tan, J. S., & Gan, C. (2022). Does independent goal interdependence impair dynamic capability? The mediating role of supplier integration and the moderating role of internal integration. Asia Pacific Journal of Marketing and Logistics, 34(7), 1436-1458.

Zarghami, S. A., & Dumrak, J. (2021). Reimaging stakeholder analysis in project management: network theory and fuzzy logic applications. Engineering, Construction and Architectural Management, 28(9), 2426-2447.




DOI: http://dx.doi.org/10.61426/sjbcm.v11i2.2992

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 3 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 2 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
 Vol 11, No 1 [2024] Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
  Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.