INFLUENCE OF PROJECT MANAGEMENT ON SUSTAINABILITY OF WATER AND SANITATION PROJECTS IN KIBRA SUB-COUNTY, KENYA

JARED MOMANYI NDUBI

Abstract


This study examined the influence of project management on sustainability of water and sanitation projects in Kibra Sub county in Nairobi County, Kenya; focusing on financial resources, stakeholder’s participation, monitoring and evaluation, and project tools and technique as the study’s specific objectives. The research adopted a descriptive research design and the target population of the study were 413 beneficiaries within the water project. Simple random sampling techniques was used to select the sample population and Krejcie morgana formula were used to determine the study sample size of 201 respondents. Pilot study was done to determine the validity and reliability of the data collection instruments. To test reliability, the Cronbach’s Alpha Test was conducted on all measures for the independent and dependent variables with a threshold of 0.7.  To establish the validity of the research instruments, the researcher sought opinion from the experts in the field of study especially the researcher’s supervisor and lecturers. Questionnaires and interview schedule were used for data collection. Data collected were coded and analyzed by IBM statistical package for Social Sciences (SPSS) version 23. The study established that a careful financial management strategy was likely to guarantee the success of water projects in the slums. Besides, there was minimal stakeholders’ participation in the implementation of water and sanitation projects hence no sense of ownership of the project. Furthermore, through proper techniques on forecasting, there was proper planning and approximation cost of the project. Besides, regular monitoring of the project and efforts to ensure that the monitoring and evaluation was as good as the project plan. There was therefore need for proper channel of resource mobilization for projects and a proper funding schedule to facilitate the completion of the water project. Also, stakeholders need to be involved in all the projects processes decision making, the mission, vision and objectives of the project. In addition, it is crucial for water projects to have a proper technique on forecasting project activities. Finally, to enhance transparency and accountability of project resources, it is important to have monitoring and evaluation. 

Key Words: Financial Resources, Stakeholder’s Participation, Monitoring And Evaluation, Project Tools And Techniques


Full Text:

PDF

References


Anderson, S., & Woodhead, R. (1981). Project Manpower Management, John Wiley, New York.

Weaver, S., & Rotman, A. (2006), Conflict of Interest in American Public Life; Harvard University Press; 2000

Asare, O. E., (2010). ‘Utilization of the multiple aspects of my IMDP learning to improve upon delays in the implementation of capital projects directly linked to production sustainability of the Obuasi Mine’. IMDP Thesis, Graduate School of Business University of Cape Town, SA.

Chu-hua, K., (2003), Tools and Methods for successful strategy missions.

Babbie, E. (2002). The basics of social research. Belmont, CA: Wadsworth Publishing.

Baccarini, D., (1996). The Concept of Project Complexity – a review. International Journal of Project Management Vol. 14(4), pp. 201-204.

Beebe, S., & Masterson, T. (2003). Communicating in small groups, Principles and practices, 8th edition, Pearson Education Inc., Boston, USA.

Berk, R. (2003). Regression analysis: A constructive critique. Thousand Oaks, CA: Sage Publications.

Blackstone, J. (2001). “Theory of constraints-A Status Report”, International Journal of Production Research, vol 39 (6), 1053-1080.

Blake, B. (1978). Managing for responsive research and development. San Francisco: Freeman and Co. Karlsen, J. (2010) Project stakeholder management.

Blismas, N., et al (2004). Factors influencing project delivery within construction client’s multi-project environments. Engineering, Construction and Architectural Management, 11 (2), 113 -125.

Blomquist, T., & Müller, R., (2006). Practices, Roles, and Responsibilities of Middle Managers in Program and Portfolio Management. Project Management Journal, 37(2), 52–66.

Bourne, L., & Walker, T. (2006). Visualizing stakeholder influence- two Australian examples. Project Management Institute, 37, 5-21.

Borum, J., & Christiansen, K., (2011). Actors and structures in IS projects. What makes implementation happen? Scandinavian Journal of Management 9,5-28.

Bowen, A., (2007). Autonomy in communication: Inclusion in strategic management and ethical decision-making, a comparative case analysis. Journal of Communication Management, 10(4), 330-3.

Bowen, A. & Ostroff, C. (2009). Understanding HRM-firm performance linkages: The role of "Strength" of the HR system. Academy of Management Review, 29, 203-22.

Boyd, L., & Gupta, M. (2004). “Constraints management: what is the theory?” International Journal of Production and Operations Management, vol. 24 (4), 350-371.

Burns, T. & Stalker, G., (1961). The Management of Innovation. (2nd Edition) London: Tavistock; 1961.

Bycio, P., Hackett, D., & Allen, J. (2005). Further assessments of Bass‘s (1985) Conceptualization of transactional and transformational leadership. Journal of Applied Psychology, 80: 468-478.

Cameron, K., & Quinn, E., (2009). Diagnosing and Changing Organization Culture. Reading, MA: Addison-Wesley.

UN-Water Annual Report (2013)

Chan, A. P. C., & Chan, A. P. L., (2004). Key Performance Indicators for measuring Construction success. Benchmarking: An International Journal 11 (2), 203-221.

WHO&UNICEF, (2015) Joint water Monitoring Programme in Africa Report.

Chao-Ming, W., (2008). A Study for the Design and Performance of the Adaptive Recommender System-Based on the Consumer’s Purchase-Decision Stage. Journal of Information Management, 10(2), pp. 19-44, 2008.

Carver, C. S., & Scheier. M. F., (1998). On the self-regulation of behavior. New York: Cambridge University Press. World Water Assessment Programme (2013)

Chatzoglou, P. D., & Macaulay, L.A., (1996). A review of existing models for project planning and estimation and the need for a new approach. International journal of project management vol 14 (3)173-183.

Cheung, S.O.; Suen, H. C. H.; & Cheung, K. W., (2004). PPMS: a Web-based construction project performance monitoring system, Automation in Construction 13: 361–376.

Cleland, D.I. & King, W.R., (1983). Systems analysis and project management. Mc Graw Hill, New York.

Cochran, W. G., (1963). Sampling Techniques, 2nd Ed New York: John Wiley and Sons, Inc. Millennium Developments Goals Report (2008), Provision of clean water and sanitation in the informal settlements in Kenya.

Cook, H.E., (1997). Product Management - Value, quality, cost, price, profit and organization. Chapman & Hall, London.

Cooper, D., & Schindler, P., (2010). Business Research methods, 12th Edition. Published by McGraw-Hill/Irwin, a business unit of The McGraw-Hill Companies, Inc.

Cooper, R.G., (2008). Perspective: the Stage-Gate idea-to-launch process update, what's new, and Nexgen Systems. The Journal of Product Innovation Management 25 (3), 213.

Cooper, H., Robinson, J. C., & Patall, E. A., (2006). Does homework improve academic achievement? A synthesis of Research 1987—2003. Review of Educational Research, 76(1), 1 - 62.

World Bank (2014), Sustainability of Water and Sanitation projects in Africa

Cooper, R.G., Edgett, S.J., Kleinschmidt, E.J., (2001). Portfolio Management for New Products. Perseus Pub, Cambridge, MA.

Cooper, R.G., Edgett, S.J., Kleinschmidt, E.J., (1999). New product portfolio management: practices and performance-an empirical survey. Journal of Product Innovation Management 16 (4), 333–351.

Crawford, P., & Bryce, P., (2003). Project monitoring and evaluation: A method of enhancing the efficiency and effectiveness of aid project implementation. International Journal of Project Management, 21(5): 363-373.

Creswell, J.W., (2003). Research Design: Qualitative, Quantitative and Mixed Methods (2nd Edition) Sage Publications.

Cronbach, L. J., (1951). Coefficient alpha and the internal structure of tests Psychometrika Vol 16, No 3.

Daft, R. L., (2010). Organization Theory and Design. Singapore: Info Access & Distribution Ltd.

Dammer, H., (2008). Multi-Project Management. GWV Fachverlage, Gabler, Wiesbaden. International Journal of Project Management, 28(8): 807-817.

Davidson, E., (2000). Ascertaining causality in theory-based evaluation, in Program Theory in Evaluation: Challenges and Opportunities. New directions for Evaluation, edited by Rogers P, Hasci T, Petrosino A, and Huebner T. Washington: World Bank:17-26.

De Man, P., (2009), "The Resistance To Theory", in David Lodge and Nigel Wood eds. Modern Criticism and Theory: A Reader (2005) pp 349–365.

Denison, D. R., (2000). Organization culture: Can it be a key lever for driving organizational change. In S. Cartwright & C. Cooper (Eds.), The Handbook of Organization culture. London: John Wiley & Sons.

Denison, D. R. & Mishra, A. K. (1995). Toward a theory of organizational culture and Effectiveness. Organization Science, 6(2), pp. 204–223.

Department of the Environment, Transport and the Regions (DETR), (2000). KPI Report for the Minister for Construction, KPI Working Group.

Dey, P. K., (2000). Managing project in a fast track: A case study of a public sector organization in India. International Journal of Public Sector Management 13(7), pp. 588–609.

Eikenberry, Angela; Klover, Jodie (Spring 2004). "The Marketization of the Nonprofit Sector: Civil Society at Risk?". Public Administration Review. 64 (2): 132–40.

Dissanayaka, S. M., & Kumaraswamy, M. M., (1999). Comparing contributors to time and cost performance in building projects, Building and Environment 34: pp. 31–42.

Drazin, R., & Van de Ven, A. H.,(1985). Alternative forms of fit in contingency theory. Admin. Sci. Quart. 1985;30:514–39.

DuBrin, A. J., (2012). Leadership: Research findings, practice, and skills. Belmont, CA: Cengage South-Western.

Dvir, D., Raz, T. & Shenhar, J., (2003). An empirical analysis of the relationship between project planning and project success, International Journal of Project Management, 21(2), pp. 1-7.

Earl, B., (2004). The practice of Social Research, International Journal of Sociology and Social Policy, Vol. 24 Iss: 3/4/5, pp.12 – 19.

Elonen, S. & Artto, .K.A, (2003). Problems in managing internal development projects in multi-project environment. International journal of project management, vol 21(6) 395-402.

Ernst, H., (2001). Corporate culture and innovative performance of a firm. Management of Engineering & Technology, 2, 532-535.

Faniran, O. O., Love, P. E. D., & Smith, J., (2000). Effective Front –End Project Management – A key Element in Achieving Project Success in Developing Countries, 2nd International Conference on construction in Developing Countries: Challenges facing the construction industry in developing countries.

Faniran, O.O., Oluwoye, J.O. & Lenard, D., (1998). Interactions between Construction planning and influence factors, Journal of Construction Engineering and Management, 124(4), 245-256.

Faridi, A. & El-Sayegh, S, (2006). Significant factors causing delay in the UAE construction industry, Construction Management and Economics 24(11): 1167–1176.

Atkin, B.; Skitmore, M. Editorial: Stakeholder management in construction. Construct. Manag. Econ. 2008, 26, 549–552

FHI., (2004). Monitoring and evaluation of Behavioral change communication programmes. Washington D.C: FHI.

Ford, H., (1926). Today And Tomorrow. Double day, Page & Co., Garden City. (Available as reprint edition: Productivity Press, Cambridge MA. 1988.) 286 p.

Furnham, A. & Gunter, B., (1993). Corporate Assessment: Auditing a Company’s Personality. London: Routlegde.

Galbraith, J., (1977). Organization design; The Academy of Management Review Vol. 3, No. 3 pp. 688-690.

Gidado, K.I. (1996). Project Complexity: The focal point of construction production planning. Construction Management and Economics, Vol 14(3), pp.213-225.

Gilbreth, F. B., & Gilbreth, L.M, (1922). Process Charts and Their Place in Management. Mechanical Engineering, January, pp. 38 - 41, 70.

Goczol, J. & Scoubeau, C., (2003). Corporate communication and strategy in the field of projects, Corporate Communications: An International Journal, Vol. 8 Iss: 1, pp.60 - 66

Goldratt, E., (1988). The Goal: The process of ongoing improvement. (3rd Revised Edition) The North River Press Publishing Corporation.

Goldratt, E. (1997). Critical Chain. Israel: The North River Press Publishing Corporation.

Golafshani, N., (2003). Understanding reliability and validity in qualitative research; The qualitative report vol 8 (4).

Ghauri, P., & Grønhaug, K., (2005). Research Methods in Business Studies: A Practical Guide, (4th Edition) Person Education Ltd, England.

Grönroos, C. (2007). Service Management and Marketing: Customer Management in Service Competition. Chichester: John Wiley & Sons.

Gyorkos, T, (2003). Monitoring and Evaluation of large scale Helminth control programmes. Acta Tropic, Vol 86(2): 275-282.

Harish, D., (2010).Performance Management Workshop Retrieved from http://www.authorstream.com.

Hopp, W., & Spearman, M., (1996). Factory Physics: Foundations of Manufacturing Management. Irwin/McGraw-Hill, Boston. 668 p.

Hyvari, I., (2006). Success of Projects in Different Organizational Condition. Project Management Journal Vol. 37, No. 4, 31-41.

Idoro, G. I., & Patunola-Ajayi J. B., (2009). Evaluating the strategies for marketing project management system in the Nigerian construction industry’, Nordic Journal of Surveying and Real Estate Research, 6(2), pp.25-36.

Ika, L. A., Diallo, A. & Thuillier, D., (2012). Critical Success Factors: An Empirical Investigation. International Journal of Project Management, 30 (2012) pp 105 116.

Iyer, K. C. & Jha, K. N., (2005). Factors influencing cost performance: evidence from Indian construction projects, International Journal of Project Management 23: pp. 283–295.

Janice, T., & Mengel, T., (2008). Preparing project managers to deal with complexity. Advanced Project Management education. International Journal of Project Management , 26 (3), 304-315.

Johnston, R.B., (1995). Making manufacturing practices tacit: a case study of computer aided production management and lean production. J. Opl. Res. Soc. 46, pp 1174-1183.

Jwan, J. & Ong’ondo, C., (2011). Qualitative Research: An introduction to principles and Techniques. Eldoret: Moi University Press.

Kandula, S. R., (2006). Performance Management. New Delhi: Prentice Hall of India private Limited.

Kerzner, H., (2009). Project Management: A Systems Approach to Planning, Scheduling, and Controlling, (10th Edition) published by John Wiley & Sons, Inc.

Klein, D. & DeBruine, M., (1995).“A Thinking Process for Establishing Management Policies”. Review of Business, vol 16, No.3:31-37.

Kopelman, R. E., Brief, A. P. & Guzzo, R. A., (1990). The role of climate and culture in productivity. In B. Schneider (Ed.), Organizational climate and culture (pp. 282- 318). San Francisco, CA: Jossey-Bass.

Koskela, L., (2000). An exploration towards a production theory and its application to construction. Espoo, VTT Building Technology. 296 p. VTT Publications; 408.

Kothari S. P., (2008). Do managers withhold bad news? Journal of Accounting research vol 47 (1) pp 241-276.

Kotnour, T., (2000). Organizational Learning practices in the project management environment. International Journal of Quality & Reliability Management, 17 (4/5), 393-406.

Kotter, J., (2012). Corporate culture and performance. New York, NY: Free Press.

Kotter, J.P. & Heskett, J.L., (2002). Corporate culture and performance. New York: The Free Press.

Kumaraswamy, M. & Chan, W. M., (1995). Determinants of Construction Duration. Construction Management and Economics 13, 209 – 217.

Kuprenas J. A., (2003). Project management actions to improve design phase cost performance, Journal of Management in Engineering, Vol. 19, No.1, PP. 25-32.

Kureshi, N., (2013). Project Performance and Contingency Theory. Journal of Strategy and Performance Management, 1(2), 46-51.

Larsson, R. & Lubatkin, M., (2001). "Achieving acculturation in mergers and acquisitions: An international case study." Human Relations Vol 54(12): 1573.

Lawrence, P.R., Lorsch, J.W., (1967). Organization and environment: managing differentiation and integration. Boston: Graduate School of Business Administration, Harvard University.

Lee, A.; Cooper R. & Aouad, G., (2001). A methodology for designing performance measures for the UK construction industry. Salford University.

Lehtonen, M. H. (2001). Resource allocation and Project Portfolio Management in Pharmaceutical R&D. In K. A. Artto, M. Martinsuo, & T. Aalto (Eds.), Project Portfolio Management: Strategic Management through Projects (pp. 107-140).

Ling, F. Y., (2004). Key determinants of performance of DBB projects in Singapore‘, Building Research and Information, Vol 32(2),128-139.

Ling, F.Y. & Chan, S.L., (2002). Performance evaluation of alternative project procurement methods. Research brief. National University of Singapore.

Lock, D., (1984). Project Management. St Martin’s press, New York.

Long, N.D., Ogunlana, S, Quang, T & Lam, K. C., (2004). Large construction projects in developing countries: a case study from Vietnam, International Journal of Project Management, Vol. 22, PP. 553–561.

Love, P. E.; Tse, R. Y. C. & Edwards, D. J., (2005). Time-cost relationships in Australian building construction projects, Journal of Construction Engineering and Management 131(2): 187–194.

Lucas, C., (2000). Setting the Scene, Humanity and Interaction. Retrieved from: www.calersco.org.

Lucas, C., (2000). The Philosophy of Complexity. Retrieved from; www.calersco.org.

Martin, C.C., (1976). Project Management. Amaco, New York.

Mbachu, J.& Nkando, R., (2007). Factors constraining successful building project implementation in South Africa, Construction Management and Economics 25(1): 39–54.

McCoy, K.L., Ngari, P. N., & Krumpe, E., (2005). Building Monitoring, Evaluation and Reporting Systems for HIV/AIDS Programs. Pact.United States of America.

Mead M. (1949). Human nature and the power of culture. A book publication on Males and Females. Washington DC, Library of Congress.

Miller, K., (2006). Organizational Communication: Approaches and Processes. Belmont, CA [etc.]: Thomson Wadsworth.

Morgan, G., (1997). Images of organization. SAGE Publications.

Morris, P.W.G., & Hough, G.H., (1987). The anatomy of major projects. John wiley and sons, New York.

Mugenda, A.G., (2008). Social Science Research. Nairobi: Acts Press.

Mugenda .& Mugenda, (.2003). Research methods; quantitative and qualitative approaches. Africa Center for Technology (ACTS), Nairobi Kenya.

Muller, R. & Turner, R. (2007). Matching the project manager’s leadership style to project type. International Journal of Project Management, 25(4), pp. 21-32.

Müller, R. & Turner, J.R., (2005). "The Impact of Principal-Agent Relationship and Contract Type on Communication between Project Owner and Manager", International Journal of Project Management, vol. 23, no. 5, pp. 398-403.

Nadler, D. (1988). Strategic Organization Design. Glenview, IL: Scott, Foresman and Co.

Naoum, S., Fong, D. & Walker, G., (2004). Critical success factors in project management; in proceedings of International Symposium on Globalization and Construction, Thailand.

Naoum, S. G., (1991). Procurement and project performance - A comparison of management and traditional contracting, CIOB occasional paper no. 45.

Nation III, G.A., (2005). Agency Law and Commercial Lending: Creating an Enforceable Security Interest. Commercial Lending Review, Vol. 20(3), pp. 17 46.

Navon, R., (2005). Automated project performance control of construction projects, Automation in Construction, Vol. 14, PP. 467– 476.

Newbold, R.C., (1998). Project Management in the fast lane. Baca Raton, FL: St Lucie Press/APICS series on constraints management.

Nielsen, Y. & Erdogan, B., (2007). Level of Visualization Support for Project Communication in the Turkish Construction Industry: A quality function Deployment Approach. Canadian Journal of Civil Engineering, Vol. 36, pp19-36.

Nsubuga, E. H. K., (2000). The teacher as a professional. Kampala: MK Publishers.

Ogbonna, E. & Harris, L., (2000). Leadership style, organizational culture and performance: Empirical evidence from UK companies. International Journal of Human Resources Management, 11(4), 766-788.

Orodho, J., (2003). Access and participation in secondary school education in Kenya. Emerging issues and policy implications. Institute of policy analysis and research.

Pallant, J., (2001). The SPSS survival manual: A step-by-step guide to data analysis using SPSS for Windows (version 10). St Leonards, NSW: Allen & Unwin

PASSIA, (2004). Civil Society empowerment: Monitoring and Evaluation. A Guide to the Project management Retrieved from: www.passia.org/seminars/2002/monitoring.htm.

Patton, M.Q., (2002). Qualitative Research and Evaluation Methods. Thousand Oaks, CA: Sage Publications.

Pennings, J.M.,(1992). Structural contingency theory: a reappraisal. Res. Organ. Behav. 1992;14:267–309.

Perrow C., (1967). A framework for the comparative analysis of organizations. Am. Sociol. Rev. 1967;32:194–208.

Pheng, L. S. & Chuan, Q. T., (2006). Environmental factors and work performance of project managers in the construction industry. International journal of project management 24: 24–37.

Pinto, J.K., (2007). Project Management: Achieving Competitive Advantage, Upper Saddle River,NJ: Pearson Education.

Pinto, J. K. & Slevin D. P., (1989). "Critical Factors in Project Implementation". Transaction of Engineering Management. Vol. 34, No.1, Pp. 22-27.

Pinto, J. K. (1986). Project Implementation: A determination of its critical success factors, moderators, and their relative importance across the project life cycle. Doctorate dissertation, University of Pittsburgh.

PMI, (2004). A guide to the Project Management Body of knowledge (PMBOK Guide), Project Management Institute, Inc. p.5.

Puthamont, S., & Charoenngam, C., (2004). Strategic project selection in public sector: Construction projects of the Ministry of Defence in Thailand‖. International Journal of Project Management, Vol. 25, Issue 2, pp.178–188.

Richardson, K., & Cilliers, P. (2001). What is complexity science? A view from different directions. Emergence, 3 (1), 5-23.

Robbins, S.P., (1996). Organizational Behavior: Concepts, controversies, applications. Seventh Edition. Prentice-Hall, New York.

Saffold, G., (1988), "Culture Traits, Strength and Organizational Performance: Moving Beyond 'Strong' Culture," Academy of Management Review, 13, 4, 546-558.

Sahlin-Andersson, K., (1992). The Social Construction of Projects. A Case Study of Organizing an Extraordinary Building Project the Stockholm Globe Arena.

Scandinavian Housing & Planning Research, Vol. 9, pp. 65-78.

Salant, P. & Dillman, D.A., (1994). How to conduct your own survey. New York.John Wiley and sons.

Samson, M. & Lema, N. M., (2005). Development of construction contractors performance measurement framework. Department of Construction Technology and Management, University of Dar es Salaam, Tanzania.

Saunders, M., Lewis, P., & Thornhill, A., (2007). Research Methods for Business Students, Financial Times/Prentice Hall, (4th Edition), UK, p. 105-108, 118, 134.

Sarshar, M. & Isikdag, U., (2004). A survey of ICT use in the Turkish construction industry", Engineering, Construction and Architectural Management, Vol. 11 Iss: 4, pp.238 – 247.

Schultz, R. L., & Slevin, D. P., (1984). Implementation and Management Innovation, in Implementing. Operations Research and Management Science, Elsevier. New York, pp. 3-22.

Sekaran, U., & Bougie, R., (2010). Research Methods for Business: A Skill Building Approach (5th ed.). West Sussex, UK: John Wiley & Sons Ltd.

Senge, P. M., (1990). The Fifth Discipline: The Art and Practice of Learning Organization, New York: Currency Doubleday.

Shenhar, A J, Levy, O, & Dvir, D., (1997). Mapping the dimension of project success. Project Management Journal, 28 (2), 5-13.

Shaker A., (2003). "The Practice of Management": Reflections on Peter F. Drucker's Landmark Book Author(s).

Shapiro, J., (2004). Monitoring and Evaluation. Johannesburg: CIVICUS.

Simon, H., (1969). The Architecture of Complexity’, Organizations: Systems, Control, and Adaptation (Vol. II). (J. Litterer, Ed.) NewYork: Wiley.

Shtub, A., & Globerson, B., (2005). Project Management: Engineering, Technology, and Implementation, International Journal of Project Management PH Inc.

Shtub, A., (1997). Project segmentation: A tool for project management. International Journal of Project Management 15(1), 15–19.

Smidts, A., Pruyn, A. H. & Riel, C., (2001). The impact of employee communication and perceived external prestige on organizational identification. Academy of Management Journal, 44, 1051-1062.

Sommerville, J., Craig, N. & McCarney, M., (2004). Document transfer and communication between distinct construction professionals‘, in proceedings of COBRA 2004 International Construction Research Conference, Leeds, 7-8 September.

Sood, S., (2003). “Taming Uncertainty: Critical- Chain buffer management helps minimize risk in the project equation”. PM Networks, vol 17(3), 56-59.

Sorensen J.N., (2002). Safety Culture, A survey of the state of of the art. Journal of the Reliability and Systems Safety Vol 76, (189-204).

Spencer, M.S. & Wathen, S., (1994). Applying the Theory of Constraints Process Management Technique to an Administrative Function at Stanley Furniture, National Productivity Review, vol 13(3), PP 379-385.

Suh, N. P., (2001). Axiomatic Design: Advances and Applications. Oxford University Press. 503 p.

Steele, L.W., (1975). Innovation in Big Business. New York: Elsevier Publishing Company.

Stukenbruck, L. C. & Zomorrodian, A., (1987). Project Management: the promise for developing countries. Journal of Project Management, vol 5(3), pp.167-175.

Teerikangas, S. & Philippe, V., (2006). The culture performance relationship in M&A. British Journal of Management vol 17 (page 31-48).

Thomas, S.R., Macken, C.L., Chung, T.H. & Kim, I. (2002). Measuring the Impact of the Delivery System on Project Performance: Design-Build and Design-Bid-Build NIST GCR 02-840. Austin, US: Construction Industry Institute.

Thompson, J.D., (1967). Organizations in Action. New York: McGraw-Hill; 1967.

Tinnirello, P.C. (2001). New Directions in Project Management. Boca Raton: Auerbach Publications.

Tom, C. (2011). Reasons Why Projects Fails: Retrieved from http://www.calosconsulting.com.

Turner, J.R. & Müller, R., (2004). "Communication and Cooperation on Projects between the Project Owner as Principal and the Project Manager as Agent", European Management Journal, vol. 21, no. 3, pp. 327-336.

Turner, J. R. & Müller, R. (2003). On the nature of the project as a temporary organization International Journal of Project Management, Vol. 21, No. 1, p. 1-8.

Turner, J. R., (1993). “The Handbook of Project-Based Management” McGraw-Hill, London, UK, p.2, 7, 50, 59, 71-72.

Ugwu, O. & Haupt, T.C., (2007). Key performance indicators and assessment methods for infrastructure sustainability, A South Africa construction industry perspective. Building and Environment 665-680.

Ugwu, O. & Kumaraswang, M., (2007). Critical success factor for construction ICT projects some empirical evidence and lessons for emerging economies. IT conference paper, 12:231–249.

Uitto, J. A., (2004). Multi-country co-operation around shared waters: Role of Monitoring and Evaluation. Global environmental change, 14(1): 5-14.

Väänänen, M., (2010), Communication in High Technology product Development Projects. Faculty of Technology, Department of Industrial Engineering and Management, University of Oulu. Acta Univ. Oul. C 364, 2010

Wallace, E., (1983). Individuals and organizations: The culture match. Training and development journal, 12, 28-36.

Westland, A., (2003), ‘Project Management Lifecycle’, London, Kogan Rage Limited.

Wheelwright, S.C., Clark, K.B., (1992). Revolutionizing Product Development. New York: The Free Press.

Williams, T.M., (1999). The need for new paradigms for complex projects. International Journal of Project Management. Vol 17(5), pp.269-273.

Wilkins, A., & Ouchi, W. G., (1983). Efficient cultures: exploring the relationship between culture and organizational performance. Administrative Science Quarterly, 28(3), 468-81.

Woodward, J., (1958) Management and technology. United Kingdom: H.M. Stationary Office.

World Bank, (2004). Infrastructure Assessment, Finance, Private Sector and Infrastructure Group, Middle East & North Africa, December 2004.

Yin, R. K., (2003). Case Study Research: design and methods, Sage Publications, UK,p. 1-6, 19-21, 34-37.

Young, N., (2009). Understanding the Research Process and Methods. An Introduction to Research Methods. Las Vegas: Acts Press.

Young, R, & Jordan, E., (2008). Top management support; Mantra or necessity. International Journal of Project Management.




DOI: http://dx.doi.org/10.61426/sjbcm.v5i2.764

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution 3.0 License.

PAST ISSUES:
20242023202220212020201920182017201620152014
Vol 11, No 4 [2024]Vol 10, No 4 [2023]Vol 9, No 4 [2022]Vol 8, No 4 [2021]Vol 7, No 4 [2020]Vol 6, No 4 [2019]Vol 5, No 4 [2018]Vol 4, No 4 [2017]Vol 3, No 4 [2016]Vol 2, No 2 [2015]Vol 1, No 2 [2014]
 Vol 11, No 3 [2024] Vol 10, No 3 [2023] Vol 9, No 3 [2022]Vol 8, No 3 [2021]Vol 7, No 3 [2020]Vol 6, No 3 [2019]Vol 5, No 3 [2019]Vol 4, No 3 [2017]Vol 3, No 3 [2016]Vol 2, No 1 [2015]Vol 1, No 1 [2014]
 Vol 11, No 2 [2024] Vol 10, No 2 [2023] Vol 9, No 2 [2022]Vol 8, No 2 [2021]Vol 7, No 2 [2020]Vol 6, No 2 [2019]Vol 5, No 2 [2018]Vol 4, No 2 [2017]Vol 3, No 2 [2016]  
 Vol 11, No 1 [2024] Vol 10, No 1 [2023] Vol 9, No 1 [2022]  Vol 8, No 1 [2021]Vol 7, No 1 [2020]Vol 6, No 1 [2019]Vol 5, No 1 [2018]Vol 4, No 1 [2017]Vol 3, No 1 [2016]   


Creative Commons License
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.